A new edition of the FIDIC Red Book is under discussion. It is an issue whether this edition should be based on the current edition or there should be a complete break with tradition in favour of a contract based on a new philosophy such as that of the NEC, which is reported to be used in many countries in circumstances in which the Red Book would otherwise have been used. This article compares the two contracts on the way they deal with site conditions issues. The comparison is on equity and clarity in risk allocation, adequacy of contractual procedures for dealing with unforeseeable conditions encountered, effectiveness of contractual machinery for dispute resolution, and compliance with reported new developments in successful contractual practices in underground construction. Studies highlighting the recurring frequency of claims for unforeseen ground conditions suggest a need for such particular attention to this aspect of construction. Although a desire for some equity in risk sharing is discernible in both contracts, there is room for improvement in the clarity of both contracts. Each contract has commendable features which are not present in the other. However, a better approach involves a combination of these features with full compliance of the reported modern developments in successful contracting practices.
Article navigation
1 February 1999
Review Article|
February 01 1999
Differing site conditions risks: a FIDIC/engineering and construction contract comparison Available to Purchase
ISSAKA NDEKUGRI;
ISSAKA NDEKUGRI
School of Engineering and the Built Environment, University of Wolverhampton, Wulfruma Street, West Midlands WV1 1SB, UK
Search for other works by this author on:
BARRY MCDONNELL
BARRY MCDONNELL
School of Engineering and the Built Environment, University of Wolverhampton, Wulfruma Street, West Midlands WV1 1SB, UK
Search for other works by this author on:
Publisher: Emerald Publishing
Online ISSN: 1365-232X
Print ISSN: 0969-9988
© MCB UP Limited
1999
Engineering, Construction and Architectural Management (1999) 6 (2): 177–187.
Citation
NDEKUGRI I, MCDONNELL B (1999), "Differing site conditions risks: a FIDIC/engineering and construction contract comparison". Engineering, Construction and Architectural Management, Vol. 6 No. 2 pp. 177–187, doi: https://doi.org/10.1108/eb021110
Download citation file:
Suggested Reading
Paths leading contractual disputes to litigation
Built Environment Project and Asset Management (August,2023)
A380 Landing gear test build
Aircraft Engineering and Aerospace Technology: An International Journal (August,2002)
Effective management strategies for construction contract disputes
International Journal of Building Pathology and Adaptation (August,2022)
What owners want from architects ‐ and how to ensure that expectations are met
Journal of Facilities Management (July,2003)
The interaction effect of trust and contract on dispute negotiation strategy: evidence from the Chinese construction industry
International Journal of Conflict Management (March,2023)
Related Chapters
The Project Manager's Perspective
Early Contractor Involvement: Improving the Management of Contract Risk
Early Contractor Involvement Models: Their Pros and Cons and When to Use Them
Early Contractor Involvement: Improving the Management of Contract Risk
Public Procurement Process
Early Contractor Involvement: Improving the Management of Contract Risk
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.