Table 5

Preliminary investigation of labour productivity and cost for PMP

ActivityCrew sizeTotal daily worker-hrsProductivity (Units/Worker)Total labour cost ($/day)Cost/Worker ($/day)
Reinforcement8643.135,120640
Formwork7523.574,420631
Concreting5225.001,760352
Crane operation1825.00960960
Finishing1825.00600600

Source(s): Authors’ own creation