Table 10

Scheduling results of case study 1

TaskEDDSPTGADQN
Task 1 (Training)Earliness ($)19442,4692003.52,122
Tardiness ($)1,33017,110890590
Total Penalty ($)3,27419,5792,893.52,712
Penalty Gap/−498.01%11.62%17.17%
Makespan (h)410410386386
Makespan Gap/0%6%6%
CPU time (s)0.370.35168.730.24
Task 2 (Rescheduling)Earliness ($)6,8376,8376,6687,336
Tardiness ($)1,6101,6101,120320
Total Penalty ($)8,4478,4477,7887,656
Penalty Gap/0.00%7.80%9.36%
Makespan (h)530530506506
Makespan Gap/0%5%5%
CPU time (s)0.470.41197.650.32
Task 3 (Rescheduling)Earliness ($)20113,5722,357.52,392.5
Tardiness ($)2,40010,7901,4101,150
Total Penalty ($)4,41114,3623,767.53,542.5
Penalty Gap/−225.60%14.59%19.69%
Makespan (h)386386362362
Makespan Gap/0%6%6%
CPU time (s)0.530.55183.710.23
Source(s): Authors’ own work