Table 3

Project delivery-related challenges and solutions of realizing energy efficiency

Challenge/barrier
Lack of/inadequate involvement of HVAC contractors and operation/maintenance people in the project definition and design phase
Fragmented (i.e. divided/isolated) procurement, project delivery, and maintenance process (multiple contracts) of energy efficient systems
Dominance of low-price criteria in the tendering process for selecting contractors which usually have low capacity to deliver their promises
Solution/enabler
Life cycle contract
Collaborative project delivery model
Involving building services people in the project definition and design phase
Involvement of client and its representative (consultant) from project definition phase until the end of the project
Early definition of the use of the building and its spaces

Source(s): Authors’ own work