Idle time and restoration task data for different DLs (adapted from Mitoulis et al. (2021))
| DL | Idle time: days | Traffic capacity of bridge after damage: % | Reinstatement time: days | Restoration tasks and prioritisation | Cost ratio (% of replacement cost of bridge) | |||||
|---|---|---|---|---|---|---|---|---|---|---|
| Min | Max | 0 days after initiation of restoration works | 3 days after initiation of restoration works | 15 days after initiation of restoration works | 30 days after initiation of restoration works | 60 days after initiation of restoration works | ||||
| Minor | 4 | 14 | 50 | 100 | 100 | 100 | 100 | 0, 3, 15, 30, 60 | R12, R5 | 5 |
| Moderate | 10 | 30 | 0 | 0 | 50 | 100 | 100 | 0, 3, 15, 30, 60 | R1, R12, R5 | 8 |
| Extensive | 25 | 45 | 0 | 0 | 0 | 100 | 100 | 0, 3, 15, 30, 60 | R1, R6, R12, R14, R2, R16, R5 | 15 |
| Severe | 30 | 70 | 0 | 0 | 0 | 0 | 100 | 0, 3, 15, 30, 60 | R1, R6, R12, R14, R2, R16, R5 | 30 |
| DL | Idle time: days | Traffic capacity of bridge after damage: % | Reinstatement time: days | Restoration tasks and prioritisation | Cost ratio (% of replacement cost of bridge) | |||||
|---|---|---|---|---|---|---|---|---|---|---|
| Min | Max | 0 days after initiation of restoration works | 3 days after initiation of restoration works | 15 days after initiation of restoration works | 30 days after initiation of restoration works | 60 days after initiation of restoration works | ||||
| Minor | 4 | 14 | 50 | 100 | 100 | 100 | 100 | 0, 3, 15, 30, 60 | R12, R5 | 5 |
| Moderate | 10 | 30 | 0 | 0 | 50 | 100 | 100 | 0, 3, 15, 30, 60 | R1, R12, R5 | 8 |
| Extensive | 25 | 45 | 0 | 0 | 0 | 100 | 100 | 0, 3, 15, 30, 60 | R1, R6, R12, R14, R2, R16, R5 | 15 |
| Severe | 30 | 70 | 0 | 0 | 0 | 0 | 100 | 0, 3, 15, 30, 60 | R1, R6, R12, R14, R2, R16, R5 | 30 |