Comparison of agile and waterfall methodologies
| Project factor | Waterfall methodology | Agile methodology |
|---|---|---|
| Requirements |
|
|
| Schedule |
|
|
| Cost |
|
|
| Quality |
|
|
| Communication |
|
|
| Customer/user involvement |
|
|
| Risk |
|
|
| Stakeholder |
|
|
| Change request |
|
|
| Deliverables |
|
|
| Business value |
|
|
| Work items |
|
|
| Workflow |
|
|
| Project team – skillset |
|
|
| Project manager |
|
|
| Documentation |
|
|
| Contract term |
|
|
| Project factor | Waterfall methodology | Agile methodology |
|---|---|---|
| Requirements | Can be defined/described or fixed | High-uncertainty or dynamic |
| Schedule | Focus on timeline | Focus on time-boxes vs sprint |
| Cost | Focus on cost | Focus on customer/user needs |
| Quality | Identified upfront | Quality can be increased/optimized for learning during the project Focus on quality and functionality at each sprint – improve patient safety |
| Communication | Solely relies on project manager to manage and provide updates to the project team | More frequent – carried out daily and at the end of the sprint – project team and customer/user can review the deliverable and provide feedback |
| Customer/user involvement | As per project milestone | High customer/user involvement during each sprint Reducing the risk of misunderstanding |
| Risk | Identified upfront | Can be identified at the start of each sprint cycle |
| Stakeholder | Identified upfront and relies on the project manager to manage from project start to finish | Can be identified and managed in a small group at a time, as per each sprint cycle |
| Change request | Restricted changes using triple constraints (scope, time and cost) and quality to measure impact | Welcome changes |
| Deliverables | Overall solution delivered at the end of the project | Customer/user can receive a subset of the overall solution during the project |
| Business value | Benefit can be realized only at the end of the project | Can benefit throughout the project, which delivers immediate value to the business |
| Work items | Identified upfront | Can be defined during the project Using small-scale experimentation Prioritization by business value ensures the most valuable features are built first Reducing the risk of complete failure |
| Workflow | Based on a fixed schedule | Based on its capacity to start work |
| Project team – skillset | Focus on subject matter experts Focus on collaboration within the project team | Focus on subject matter experts, teamwork and interpersonal skills Focus on cross-functional teams and increased collaboration |
| Project manager | Dedicated project manager for managing project and project team | Using a team facilitator to facilitate collaboration and coaching |
| Documentation | Identified upfront | Can be identified at the start of each sprint cycle |
| Contract term | Suitable for fixed fee | Suitable for time and material May not permit partial deliverables if the project is terminated |
Key takeaway: the comparison shows that waterfall methodologies emphasize upfront planning, fixed scope and structured processes, whereas agile methodologies prioritize flexibility, iterative development and continuous stakeholder engagement. This contrast establishes the rationale for hybrid approaches, which blend predictability with adaptability in contexts such as humanitarian projects