Cost estimate classification and the expected accuracy rate of costs

Estimate classMaturity level of project definition deliverablesEnd usageMethodologyExpected accuracy rate
Class 50%–2%Functional area or concept screeningStochastic factors or quantity-based factoring, parametric models, judgement or analogyL: - 20% to −30% H: +30% to 50%
Class 41%–15%Schematic design or concept studyParametric models, assembly driven modelsL: −10% to −20% H: + 30% to + 50%
Class 310%–40%Design development, budget authorisation, feasibilitySemi-detailed unit costs with assembly level line itemsL: −5% to −15% H: + 10% to + 20%
Class 230%–75%Control or bid/tender, semi-detailedDetailed unit cost with forced detailed take-offL: −5% to −10% H: + 5% to + 15%
Class 160%–100%Check estimate or pre bid/tender, change orderDetailed unit costs with detailed take-offL: −3% to −5% H: + 3% to + 10%
Source(s): Adapted from AACE, 2020 