Overview of the main results in tool design
| Steps of tool design | Discussion within the article | Total project lead time (TPT) – hours | Total project cost (TPC) – CT$ |
|---|---|---|---|
| The sample release plan | 4.1 | 80 | 2139.22 |
| Simulation of the current sample release process٭ | 4.2 | 160.4 | 4109.02 |
| Scrum simulation٭ | 5.1.1 | 123.9 | 3230.07 |
| The process built upon Scrum and Google Docs (simulation)٭ | 5.1.2 | 111.2 | 2819.21 |
| Accomplished rationalization of the software dev. process with Scrum and Google Docs (mean values after 17 cycles) | 5.2 | 118.9 | 2950.20 |
| Steps of tool design | Discussion within the article | Total project lead time (TPT) – hours | Total project cost (TPC) – CT$ |
|---|---|---|---|
| The sample release plan | 4.1 | 80 | 2139.22 |
| Simulation of the current sample release process٭ | 4.2 | 160.4 | 4109.02 |
| Scrum simulation٭ | 5.1.1 | 123.9 | 3230.07 |
| The process built upon Scrum and Google Docs (simulation)٭ | 5.1.2 | 111.2 | 2819.21 |
| Accomplished rationalization of the software dev. process with Scrum and Google Docs (mean values after 17 cycles) | 5.2 | 118.9 | 2950.20 |
Note(s): ٭Results reported with a 95% significance level
Source(s): By authors