Table 3

Operational performance indicators for the G208 reconstruction project

CategoriesSub-categoriesIndicatorsScoreEvaluation criteriaScoring methodology
OutputProject OperationRoad Network Information Services5Timely and accurate release of travel and road condition information3 points awarded for information releases that are timely, accurate, and compliant with regulatory requirements. Each instance of untimely or inaccurate release results in a deduction of 1 point, up to a maximum deduction of 5 points
Station Area Management51. Clean and tidy toll plaza environment without debris or garbage; facilities intact, clean, and undamaged.
2. Normal operation of toll lane equipment and facilities
1. 0.5 points deducted per instance of unclean plaza, debris, damaged safety islands, zebra crossing paint peeling, canopy damage, or improper barrier placement (max 2 points)
2. 1 point deducted per unresolved equipment malfunction or network outage (max 3 points)
Toll Management101. Implementation of “Five Disclosures” (toll standards, approving authority, supervision hotline, social commitments, toll operator)
2. Standardized toll records management and strict adherence to approved charging standards
1. 1 point deducted per missing disclosure item (max 2 points)
2. 3 points deducted for irregular record-keeping
3. 5 points deducted for non-compliance with approved standards
Project MaintenanceMaintenance System101. Annual/monthly maintenance planning and implementation
2. Emergency response plans for disasters/special weather
3. Complete inspection records with signatures
4. Timely post-rain inspections and repairs
5. 24-h issuance of repair orders for identified defects
1. 1 point deducted per non-compliance item (max 2 points)
2. 1 point deducted per non-compliance (max 2 points)
3. 1 point deducted per incomplete/unverified record (max 2 points)
4. 1 point deducted per non-compliance (max 2 points)
5. 2 points deducted per failure (max 2 points)
Maintenance Quality25Comprehensive evaluation of road maintenance quality meeting contractual requirements, with rectification plans for deficienciesFull score awarded when Pavement Quality Index (PQI), Subgrade Condition Index (SCI), Bridge/Tunnel Condition Index (BCI), and Traffic Facilities Index (TCI) all ≥80. Otherwise, no points awarded
Maintenance Inspections141. Smooth pavement without defects
2. Intact bridge facilities
3. Well-maintained roadside vegetation
4. Complete ancillary facilities
1. 0.5 points deducted per pavement defect (max 5)
2. 0.5 points deducted per bridge defect (max 5)
3. 0.5 points deducted per vegetation issue (max 1)
4. 0.5 points deducted per facility defect (max 3)
Safety AssuranceSafety Management System41. Established safety organization with dedicated personnel
2. Comprehensive safety regulations
1. 1 point deducted per missing organizational element (max 2)
2. 1 point deducted per regulatory deficiency (max 2)
Accident Handling81. Compliance with accident reporting requirements
2. Proper investigation and reporting of major incidents
1. 2–4 points deducted for reporting violations
2. 1–4 points deducted for investigation/reporting failures
Emergency Plans41. Comprehensive emergency plans with resource inventories
2. Regular emergency drills
1. 1 point deducted per planning deficiency (max 2)
2. 2 points deducted for drill non-compliance
OutcomeEcological ImpactEnergy Conservation11. Adoption of energy-efficient lighting
2. ≥80% asphalt recycling rate
0.5 points deducted per unmet criterion
Environmental Penalties2Compliance with environmental regulations1 point deducted per penalty received (max 2)
Social ImpactPublic Sentiment21. Effective complaint resolution
2. Avoidance of media exposure
3. Prevention of major incidents
Full deduction for major exposures; partial deductions for minor issues
Travel Assurance2Implementation of traffic maintenance plans1 point deducted per significant traffic disruption
SatisfactionPublic Satisfaction3Public satisfaction survey results1 point base score; 0.1 points deducted per 1% below 80% satisfaction
ManagementRegulatory ComplianceTax Compliance2Timely tax filingFull deduction for non-compliance
Records ManagementArchiving System11. Complete archival system
2. Dedicated personnel
3. Proper document control
0.5 points deducted per deficiency (max 1)
Information DisclosureTimely Disclosure2Policy-compliant information sharingFull deduction for non-compliance