Case study scenario – definitions regarding CE KPIs
| Key CE parameters | Case study scenario |
|---|---|
| Construction method | Retrofitting/Reusing of an existing building structure |
| Materials sources | Remanufactured/Bio-based materials (such as reclaimed natural timber for framing, studs, and joints, and sheep’s wool batts for insulation) |
| CE design practices consideration | Modular building system- prefabricated three-dimensional modules (e.g. wall panels, roof trusses) manufactured offsite and assembled onsite |
| Using dry, mechanical connections for easy disassembly of components | |
| A comprehensive take-back system is in place for all components | |
| Construction waste destination | Materials are reused/recycled/remanufactured |
| Site condition | Built on a previously occupied site |
| Key CE parameters | Case study scenario |
|---|---|
| Construction method | Retrofitting/Reusing of an existing building structure |
| Materials sources | Remanufactured/Bio-based materials (such as reclaimed natural timber for framing, studs, and joints, and sheep’s wool batts for insulation) |
| CE design practices consideration | Modular building system- prefabricated three-dimensional modules (e.g. wall panels, roof trusses) manufactured offsite and assembled onsite |
| Using dry, mechanical connections for easy disassembly of components | |
| A comprehensive take-back system is in place for all components | |
| Construction waste destination | Materials are reused/recycled/remanufactured |
| Site condition | Built on a previously occupied site |