Disassembly costs and resale value per gross floor area (€/m2, GFA) and the resale value ratio required for economic feasibility
| D | s | ||
|---|---|---|---|
| Design solution | Additional disassembly costs compared to crushing demolition method | Initial cost of reusable building components recovered (Module D) | Required resale value ratio to initial cost to make disassembly profitable |
| BAU-R | 191 | 77 | 248% |
| DfD-W | 138 | 169 | 82% |
| DfD-I | 96 | 169 | 57% |
| D | s | ||
|---|---|---|---|
| Design solution | Additional disassembly costs compared to crushing demolition method | Initial cost of reusable building components recovered (Module D) | Required resale value ratio to initial cost to make disassembly profitable |
| BAU-R | 191 | 77 | 248% |
| DfD-W | 138 | 169 | 82% |
| DfD-I | 96 | 169 | 57% |