Categorisation of issues in procurement and management of BSSs based on expert feedback
| Issue number | Issues in the procurement and management of BSSs | Criticality of issues | Expert agreement (%) | ||
|---|---|---|---|---|---|
| Major | Moderate | Minor | |||
| IS1: Stakeholder coordination and trust issues | |||||
| C1 | Overinvolvement of stakeholders in the building services process leads to numerous clashes | √ | 84.2 | ||
| C2 | Difficulty in establishing trust among stakeholders | √ | 78.9 | ||
| C3 | Difficulty in managing workflow due to a lack of collaboration among parties | √ | 89.5 | ||
| C4 | Conflicts in contracts | √ | 87.5 | ||
| C5 | Delays in approvals | √ | 78.9 | ||
| IS2: Regulatory compliance and governance issues | |||||
| C6 | Noncompliance with building practitioner regulations | √ | 16.7 | ||
| C7 | Lack of adherence to government regulations | √ | 25 | ||
| C8 | Not complying with quality standards | √ | 33.3 | ||
| C9 | Lack of transparency in the manufacturing procedure | √ | 53.8 | ||
| C10 | Clashes between design and specifications | √ | 58.3 | ||
| IS3: Data integrity and transparency issues | |||||
| C11 | Difficulty in exchanging data (e.g. drawings, project info) | √ | 78.9 | ||
| C12 | Poor decision-making due to inaccurate/lack of information | √ | 53.8 | ||
| C13 | Inconsistencies between the documentation | √ | 50 | ||
| C14 | Lack of transparency in working processes | √ | 77.8 | ||
| IS4: Procurement and operational workflow issues | |||||
| C15 | Low quotation-to-order ratio | √ | 58.3 | ||
| C16 | Long and complicated tendering processes | √ | 70 | ||
| C17 | Supply risks in procurement | √ | 75 | ||
| C18 | Large-scale dark purchasing | √ | 12.5 | ||
| C19 | Risks associated with insurance | √ | 77.8 | ||
| C20 | Issues with equipment delivery | √ | 76.9 | ||
| C21 | Issues in service provision | √ | 50 | ||
| C22 | Warranty leakages | √ | 50 | ||
| C23 | Lack of proper inspections | √ | 70 | ||
| IS5: Design requirement issues | |||||
| C24 | Unclear conceptual designs | √ | 53.8 | ||
| C25 | Instantaneous design changes | √ | 58.3 | ||
| C26 | Unclear client requirements | √ | 69.2 | ||
| C27 | Sudden changes in the client’s requirements | √ | 66.7 | ||
| C28 | Incompatibility among design software | √ | 21.4 | ||
| Issue number | Issues in the procurement and management of BSSs | Criticality of issues | Expert agreement (%) | ||
|---|---|---|---|---|---|
| Major | Moderate | Minor | |||
| C1 | Overinvolvement of stakeholders in the building services process leads to numerous clashes | √ | 84.2 | ||
| C2 | Difficulty in establishing trust among stakeholders | √ | 78.9 | ||
| C3 | Difficulty in managing workflow due to a lack of collaboration among parties | √ | 89.5 | ||
| C4 | Conflicts in contracts | √ | 87.5 | ||
| C5 | Delays in approvals | √ | 78.9 | ||
| C6 | Noncompliance with building practitioner regulations | √ | 16.7 | ||
| C7 | Lack of adherence to government regulations | √ | 25 | ||
| C8 | Not complying with quality standards | √ | 33.3 | ||
| C9 | Lack of transparency in the manufacturing procedure | √ | 53.8 | ||
| C10 | Clashes between design and specifications | √ | 58.3 | ||
| C11 | Difficulty in exchanging data (e.g. drawings, project info) | √ | 78.9 | ||
| C12 | Poor decision-making due to inaccurate/lack of information | √ | 53.8 | ||
| C13 | Inconsistencies between the documentation | √ | 50 | ||
| C14 | Lack of transparency in working processes | √ | 77.8 | ||
| C15 | Low quotation-to-order ratio | √ | 58.3 | ||
| C16 | Long and complicated tendering processes | √ | 70 | ||
| C17 | Supply risks in procurement | √ | 75 | ||
| C18 | Large-scale dark purchasing | √ | 12.5 | ||
| C19 | Risks associated with insurance | √ | 77.8 | ||
| C20 | Issues with equipment delivery | √ | 76.9 | ||
| C21 | Issues in service provision | √ | 50 | ||
| C22 | Warranty leakages | √ | 50 | ||
| C23 | Lack of proper inspections | √ | 70 | ||
| C24 | Unclear conceptual designs | √ | 53.8 | ||
| C25 | Instantaneous design changes | √ | 58.3 | ||
| C26 | Unclear client requirements | √ | 69.2 | ||
| C27 | Sudden changes in the client’s requirements | √ | 66.7 | ||
| C28 | Incompatibility among design software | √ | 21.4 | ||