Stability of top delay factors under cross-validation of expert weights
| ID | Delay risk factor | Weight (%) | Weight range | Variation percentage (%) |
|---|---|---|---|---|
| 1 | Consultant's lack of experience | 11.5 | [10.9%,12.1%] | 100 |
| 2 | Contractor's financial problems | 9.3 | [8.8%,9.8%] | 100 |
| 3 | Poor qualification of the contractors' technical staff | 7.4 | [7.1%,7.9%] | 100 |
| 4 | Owner's lack of experience | 6.5 | [6.2%,6.9%] | 100 |
| 5 | Owner's financial problems | 5.6 | [5.3%,5.9%] | 100 |
| 6 | Owner's late decisions | 5.4 | [5.1%,5.7%] | 100 |
| 7 | Owner's change in requirements | 5.1 | [4.8%,5.4%] | 100 |
| 8 | Delay in changes approval | 3.7 | [3.5%,3.9%] | 100 |
| 9 | Delay in sub-contractor's work | 3.5 | [3.3%,3.7%] | 100 |
| 10 | Shortage of labour | 3.2 | [3.1%,3.4%] | 100 |
| 11 | Labour productivity | 3.2 | [3.0%,3.4%] | 100 |
| 12 | Poor project cost estimation | 3.2 | [3.0%,3.4%] | 100 |
| 13 | Poor and improper planning | 3.0 | [2.9%,3.2%] | 100 |
| 14 | Complexity in project design | 2.9 | [2.7%,3.1%] | 99 |
| 15 | Late in revising and approving design documents | 2.9 | [2.7%,3.0%] | 100 |
| 16 | Unclear and inadequate details in drawings | 2.8 | [2.6%,3.0%] | 100 |
| 17 | Lack of coordination | 2.8 | [2.6%,2.9%] | 98 |
| 18 | Mistakes during the execution of works | 2.8 | [2.6%,2.9%] | 98 |
| 19 | Injuries on site | 2.8 | [2.6%,2.9%] | 99 |
| 20 | Poor project management and supervision | 2.7 | [2.6%,2.9%] | 98 |
| 21 | Inflation | 2.7 | [2.5%,2.8%] | 95 |
| 22 | Rainfall and weather conditions | 2.6 | [2.5%,2.7%] | 93 |
| ID | Delay risk factor | Weight (%) | Weight range | Variation percentage (%) |
|---|---|---|---|---|
| 1 | Consultant's lack of experience | 11.5 | [10.9%,12.1%] | 100 |
| 2 | Contractor's financial problems | 9.3 | [8.8%,9.8%] | 100 |
| 3 | Poor qualification of the contractors' technical staff | 7.4 | [7.1%,7.9%] | 100 |
| 4 | Owner's lack of experience | 6.5 | [6.2%,6.9%] | 100 |
| 5 | Owner's financial problems | 5.6 | [5.3%,5.9%] | 100 |
| 6 | Owner's late decisions | 5.4 | [5.1%,5.7%] | 100 |
| 7 | Owner's change in requirements | 5.1 | [4.8%,5.4%] | 100 |
| 8 | Delay in changes approval | 3.7 | [3.5%,3.9%] | 100 |
| 9 | Delay in sub-contractor's work | 3.5 | [3.3%,3.7%] | 100 |
| 10 | Shortage of labour | 3.2 | [3.1%,3.4%] | 100 |
| 11 | Labour productivity | 3.2 | [3.0%,3.4%] | 100 |
| 12 | Poor project cost estimation | 3.2 | [3.0%,3.4%] | 100 |
| 13 | Poor and improper planning | 3.0 | [2.9%,3.2%] | 100 |
| 14 | Complexity in project design | 2.9 | [2.7%,3.1%] | 99 |
| 15 | Late in revising and approving design documents | 2.9 | [2.7%,3.0%] | 100 |
| 16 | Unclear and inadequate details in drawings | 2.8 | [2.6%,3.0%] | 100 |
| 17 | Lack of coordination | 2.8 | [2.6%,2.9%] | 98 |
| 18 | Mistakes during the execution of works | 2.8 | [2.6%,2.9%] | 98 |
| 19 | Injuries on site | 2.8 | [2.6%,2.9%] | 99 |
| 20 | Poor project management and supervision | 2.7 | [2.6%,2.9%] | 98 |
| 21 | Inflation | 2.7 | [2.5%,2.8%] | 95 |
| 22 | Rainfall and weather conditions | 2.6 | [2.5%,2.7%] | 93 |