Cross-validation of localised delay risk factors with prior Australian studies
| No. | Delay risk factor | Derakhshanfar et al. (2021) | Al-Kilidar and Hasib (2021) | Basak et al. (2019) |
|---|---|---|---|---|
| 1 | Consultant's lack of experience | ✔ | ✔ | |
| 2 | Contractor's financial problems | ✔ | ||
| 3 | Poor qualification of the contractors' technical staff | ✔ | ✔ | |
| 4 | Owner's lack of experience | ✔ | ||
| 5 | OWNER's financial problems | ✔ | ✔ | |
| 6 | Owner's Late Decisions | ✔ | ||
| 7 | Owner's change in requirements | ✔ | ||
| 8 | Delay in changes approval | ✔ | ||
| 9 | Delay in sub-contractor's work | ✔ | ✔ | |
| 10 | Shortage of labour | ✔ | ||
| 11 | Labour productivity | ✔ | ||
| 12 | Poor project cost estimation | ✔ | ||
| 13 | Poor and improper planning | ✔ | ||
| 14 | Complexity in project design | ✔ | ||
| 15 | Late in revising and approving design documents | ✔ | ✔ | |
| 16 | Unclear and inadequate details in drawings | ✔ | ||
| 17 | Lack of coordination | ✔ | ✔ | |
| 18 | Mistakes during the execution of works | ✔ | ✔ | |
| 19 | Injuries on site | |||
| 20 | Poor project management and supervision | ✔ | ✔ | |
| 21 | Inflation | ✔ | ||
| 22 | Rainfall and weather conditions | ✔ |
| No. | Delay risk factor | |||
|---|---|---|---|---|
| 1 | Consultant's lack of experience | ✔ | ✔ | |
| 2 | Contractor's financial problems | ✔ | ||
| 3 | Poor qualification of the contractors' technical staff | ✔ | ✔ | |
| 4 | Owner's lack of experience | ✔ | ||
| 5 | OWNER's financial problems | ✔ | ✔ | |
| 6 | Owner's Late Decisions | ✔ | ||
| 7 | Owner's change in requirements | ✔ | ||
| 8 | Delay in changes approval | ✔ | ||
| 9 | Delay in sub-contractor's work | ✔ | ✔ | |
| 10 | Shortage of labour | ✔ | ||
| 11 | Labour productivity | ✔ | ||
| 12 | Poor project cost estimation | ✔ | ||
| 13 | Poor and improper planning | ✔ | ||
| 14 | Complexity in project design | ✔ | ||
| 15 | Late in revising and approving design documents | ✔ | ✔ | |
| 16 | Unclear and inadequate details in drawings | ✔ | ||
| 17 | Lack of coordination | ✔ | ✔ | |
| 18 | Mistakes during the execution of works | ✔ | ✔ | |
| 19 | Injuries on site | |||
| 20 | Poor project management and supervision | ✔ | ✔ | |
| 21 | Inflation | ✔ | ||
| 22 | Rainfall and weather conditions | ✔ |