Loading for PC of risks associated with ADPMs
| No. | Risk | Acronym | PC1 | PC2 | PC3 | PC4 | PC5 |
|---|---|---|---|---|---|---|---|
| 1 | Change in scope (e.g. due to coordination with third parties; late change requests) | C1 | −0.293 | 0.208 | −0.187 | 0.049 | −0.227 |
| 2 | Conformance with regulations/guidelines/design criteria | C2 | −0.201 | 0.014 | 0.682 | 0.216 | 0.091 |
| 3 | Constructability issues | C3 | −0.317 | 0.145 | 0.352 | −0.065 | −0.372 |
| 4 | Coordination with government agencies or other authorities having jurisdiction | C4 | −0.133 | 0.631 | 0.035 | −0.105 | 0.049 |
| 5 | Environmental permits and approvals | E | −0.270 | 0.242 | 0.168 | 0.215 | 0.414 |
| 6 | Financial issues | F | −0.348 | −0.273 | 0.095 | −0.218 | 0.284 |
| 7 | Geotechnical conditions | G | −0.261 | −0.104 | 0.101 | 0.164 | −0.094 |
| 8 | Incomplete project scope definition/design uncertainty | I | −0.262 | 0.061 | −0.374 | 0.420 | −0.184 |
| 9 | Legal challenges and changes in law | L | −0.282 | −0.163 | −0.237 | 0.202 | 0.340 |
| 10 | Market conditions (e.g. price volatility, labor availability, etc.) | M | −0.223 | −0.289 | 0.116 | −0.430 | −0.430 |
| 11 | Political risks/opposition | P | −0.319 | −0.049 | −0.272 | −0.328 | 0.082 |
| 12 | Right-of-way and easements | R | −0.199 | 0.147 | −0.084 | −0.494 | 0.351 |
| 13 | Schedule/phasing issues (aggressive schedule, restricted work window, etc.) | S | −0.324 | 0.154 | −0.191 | 0.106 | −0.266 |
| 14 | Use of new procurement methods/contracts | U | −0.219 | −0.482 | 0.005 | 0.226 | 0.057 |
| No. | Risk | Acronym | PC1 | PC2 | PC3 | PC4 | PC5 |
|---|---|---|---|---|---|---|---|
| 1 | Change in scope (e.g. due to coordination with third parties; late change requests) | C1 | −0.293 | 0.208 | −0.187 | 0.049 | −0.227 |
| 2 | Conformance with regulations/guidelines/design criteria | C2 | −0.201 | 0.014 | 0.682 | 0.216 | 0.091 |
| 3 | Constructability issues | C3 | −0.317 | 0.145 | 0.352 | −0.065 | −0.372 |
| 4 | Coordination with government agencies or other authorities having jurisdiction | C4 | −0.133 | 0.631 | 0.035 | −0.105 | 0.049 |
| 5 | Environmental permits and approvals | E | −0.270 | 0.242 | 0.168 | 0.215 | 0.414 |
| 6 | Financial issues | F | −0.348 | −0.273 | 0.095 | −0.218 | 0.284 |
| 7 | Geotechnical conditions | G | −0.261 | −0.104 | 0.101 | 0.164 | −0.094 |
| 8 | Incomplete project scope definition/design uncertainty | I | −0.262 | 0.061 | −0.374 | 0.420 | −0.184 |
| 9 | Legal challenges and changes in law | L | −0.282 | −0.163 | −0.237 | 0.202 | 0.340 |
| 10 | Market conditions (e.g. price volatility, labor availability, etc.) | M | −0.223 | −0.289 | 0.116 | −0.430 | −0.430 |
| 11 | Political risks/opposition | P | −0.319 | −0.049 | −0.272 | −0.328 | 0.082 |
| 12 | Right-of-way and easements | R | −0.199 | 0.147 | −0.084 | −0.494 | 0.351 |
| 13 | Schedule/phasing issues (aggressive schedule, restricted work window, etc.) | S | −0.324 | 0.154 | −0.191 | 0.106 | −0.266 |
| 14 | Use of new procurement methods/contracts | U | −0.219 | −0.482 | 0.005 | 0.226 | 0.057 |