Table A1

Alberta's P3 program emergence and evolution profile (2002–2022)

YearPolicy interventions/frameworksProjects/events
2002Establishment of the Panel on Fiscal Reform–Financial Management Commission (FMC)Published RFQ for the South East Anthony Henday Drive
2003Acceptance and publication of the report of the FMCPublished RFP for the South East Anthony Henday Drive
2004Amendment of the Fiscal Responsibility Act to accommodate P3s for public assets deliverySigned contract for the South East Anthony Henday Drive
2005Cabinet approval of the new P3 policy for capital projects and alternative capital projectsCommissioning of the South West Anthony Henday Drive (Conventional model)
2006Publication of the first P3 GuidelinesCommissioning of the South East Anthony Henday Drive
2007Publication of the second P3 GuidelinesAwarded a P3 contract for the North East Stoney Trail, Calgary
2008Establishment of the Alternative Capital Financing Office (ACFO)Awarded P3 contract for the North West Anthony Henday Drive
  Award contract for the first P3 18 schools
2009Publication of the third and most comprehensive P3 GuidelinesCommissioning of the North East Stoney Trail, Calgary
2010Commissioning of the first 18 P3 schools
2011Commissioning of the North West Anthony Henday Drive
2012North East Anthony Henday Drive RFQ and RFP out to tender
2013Award of the contract for the North East Anthony Henday Drive
2016Construction begins on the North East Anthony Henday Drive
2021Commissioning of the South East Stoney Trail, Calgary
 Commisioning of the North East Anthony Henday Drive, Edmonton
 Award of the South West Stoney Trail contract–Calgary
 Estimated completion of the South West Stoney Trail contract–Calgary
2021New P3 policy enunciationEstablishment of a new P3O Office
Publication of the Unsolicited Project Policy Guidelines

Source(s): Authors' compilation, 2022