TableĀ 2

Responses on project initiation

StatementsMeanSD
1I believe the project is in the best interest of the organisation4.880.33
2All the information that was needed was provided by the organisation4.860.35
3The project team was constituted in a proper manner4.380.70
4The project's scope was well defined4.131.27
5I clearly understood how the project was going to be executed4.130.93
6The project plan and schedule were well-documented4.001.12
7I understood everyone's responsibilities3.501.32
8I had a clear idea of what the outcome would be from the project3.381.32
9The allocated time for the project was adequate2.501.32