Table II

Short-term design control data for T1 and T2

Design teamsDesign phaseNumber of weeksAverage PPC (%)Causes for the non-completion of work packagesCategories of causes
T1Detail design2676Client delay in design decisions: 25%
Client delay in design approval: 18%
Underestimated time: 12%
EDD processes: 25%
Other company’s departments: 26%
External to the company: 49%
T2Detail design3979Client request for design change: 23%
Client delay in design approval: 15%
Conceptual design delay: 15%
EDD processes: 19%
Other company’s departments: 29%
External to the company: 52%