Table 1.

Choice of case hospital projects, their location, type of project, stage of the project as well as size, no. of patient beds and estimated construction cost

Case 1Case 2Case 3Case 4Case 5Case 6Case 7Case 8
Stage of the project (phase)OperationDesign and constructionOperationDesignDesignDesignDesignDesign
Accomplished (year)20152021201820242023202520242023
Health authority (HF) and regionHF Sør-ØstHF Sør-ØstHF MidtHF MidtHF Sør-ØstHF Sør-ØstHF Sør-ØstHF Vest
No of inhabitants in region317 000230 000137 000130 000300 000500 500 470 000
New somatic or psychiatric hospitalBothBothPsychiatricBothPsychiatricBothSomaticSomatic
Type of project:
New location, extension or addition
NewExtension, refurbishment and new additionExtension and refurbishmentNewNewNewExtension and refurbishmentNew
Size (BTA m2)9200011 300 +
33 000
600 + 200060 00010 760122 00043 000100 000
No. of patient beds (psych. + somatic)71250 + 1766039 + 19780167 + 378153640
No. of m2/beds12919243,3254134,3224215156
Construction + refurbishment cost (2016 cost, MRD NOK)6,12,70,4**4,6***0,87**8,23,06 + 1,71 *9,2 **

Note:

*2018, **2019 level, ***2020 levels