Project charter
| Problem statement | Goal statement | Project scope |
|---|---|---|
| Significant cash deficit in the previous 18 month lead to company to spend lot of money in bank interest | €120,000 savings per year | The project is scoped for suppliers’ management |
| Project metric/CTQ | Project team | Project timeline |
| y: Creditor days at cash critical times. Defect = invoice paid at less than contract terms in cash-critical month | - Black belt (J.B.) - Master black belt (R.S.) - Sponsor (F.V.) - Finance team (2 people) - Purchasing team (2 people) | 6 month |
| Problem statement | Goal statement | Project scope |
|---|---|---|
| Significant cash deficit in the previous 18 month lead to company to spend lot of money in bank interest | €120,000 savings per year | The project is scoped for suppliers’ management |
| Project team | Project timeline | |
| - Black belt (J.B.) | 6 month |