Table 21

Example service and resilience targets for an earthquake event

Intervention costs/service measuresTarget typeDescriptionTargetMeasurement
Intervention costsMaximum increase in intervention costsThe costs of the emergency measuresMaximum emergency budget: €2 000 000 per eventBy way of the bookkeeping system of the infrastructure owner
Maximum total intervention costsThe total costs incurred until the travel time service is returned to normalMaximum total costs: €4 500 000 per event
     
Travel timeMaximum decrease in serviceThe increase of travel time after an earthquake eventBelow 45 min per tripBy way of automated traffic flow monitoring system
Shape of losses of service curve during restorationThe way in which travel time returns to normal after an earthquake eventWithin 1 week after the earthquake: max delay of 30 min per trip
Within 3 weeks after the earthquake: max delay of 15 min per trip
Maximum allowed restoration timeThe total time from onset of the earthquake event until normal travel timeWithin 12 weeks after the earthquake: no traffic delays