Table 5

Typical pile testing strategy based on risk levels

Characteristics of the piling worksRisk levelPile testing strategy
Complex or unknown ground conditions
No previous pile test data
New piling technique or very limited relevant experience
HighBoth preliminary and working pile tests are essentials
One preliminary pile test per 250 piles
One working pile test per 100 piles
Consistent ground conditions
No previous pile test data
Limited experience of piling in similar ground
MediumPile tests essential; either preliminary and/or working pile tests can be used
One preliminary pile test per 500 piles
One working pile test per 100 piles
Previous pile test data are available
Extensive experience of piling in similar ground
LowPile tests not essential; if using pile tests, either preliminary and/or working tests can be used
One preliminary pile test per 500 piles
One working pile test per 100 piles