The summary of the Murrayfield Stadium project
| Project | Murrayfield Stadium, Edinburgh, UK |
|---|---|
| When | 2018 |
| Aim | Optimising the crowd throughput |
| Problem | A new building was developing – would the crowd adapt to the new environment? There were two minor injuries on site – were the existing safety procedures adequate? |
| Solution | The use of DIM-ICE risk model assisted in analysing the current situation and providing a set of recommendation |
| Benefits | >90% of Murrayfield Stadium’s safety operations were appropriate Areas that required improvement regarding the existing risk assessment policy were identified The design of the queuing system was improved to achieve the more efficient inflow Murrayfield Stadium demonstrate continual assessment and improvement to the risk management process Customer satisfaction was enhanced |
| People impacted by the project recommendations | 67,000 per event |
| Project | Murrayfield Stadium, Edinburgh, UK |
|---|---|
| When | 2018 |
| Aim | Optimising the crowd throughput |
| Problem | A new building was developing – would the crowd adapt to the new environment? |
| Solution | The use of DIM-ICE risk model assisted in analysing the current situation and providing a set of recommendation |
| Benefits | >90% of Murrayfield Stadium’s safety operations were appropriate |
| People impacted by the project recommendations | 67,000 per event |
Sharing content requires targeting cookies to be enabled. Please update your cookie preferences to use this feature.