Table 1

Summary of the OM framework as defined in C760 (Table 7.2 of Gaba et al. (2017))

OM approachAb initio (from the start)Ipso tempore (in the moment)
A – optimistic (Peck, 1969)B – cautious (Ciria R185 (Nicholson et al., 1999))C – proactiveD – reactive (Peck, 1969)
When does OM design work start?Before wall constructionAfter wall construction
Starting design assumptionsMost probable parametersCharacteristic parametersNecessary, from back-analysis of initial stages
Back-analysis requirementsNecessary, with reliable case study dataPreferredUse initial construction stages
Design objectivesOptimise wall depth/strength supportOptimise wall supportReduce wall supportIncrease wall support
Alternative design plansUse contingency planUse modification planIntroduce modification planIntroduce contingency plan