Table 6.

Initial investment superstructure costs

Project development costs (excluding VAT)Total ZAR
Ship to shore cranes × 5540.04
Rubber tired gantry cane × 15286.74
Rail-mounted gantry crane × 274.75
Haulers × 20 (prime mover equipment)19.53
Hauler trailers × 20 (prime mover support)14.84
Empty container handler × 412.18
Reach stackers × 28.85
Forklift 15t × 12.57
Forklift 7t × 21.70
Forklift 5 ton × 10.78
Additional STS crane spreaders × 46.77
Cherry picker × 11.16
Headblock × 40.78
Heavy lift hook (heavy lift) × 10.44
Out of gauge spreader0.78
IT network and systems58.75
Buildings and other superstructure440.97
Total development costs (ex VAT)1,471.64