Table 2

LPS’s adaptations to suit the retrofit context (Kemmer et al., 2016)

LPS elementPhase 1B
Long-term (master plan)Devised in a collaborative fashion by the delivery team through the use of Post-it notes and a location-based chart
Phase planning
Medium-term (look-ahead plan)Constraints were listed for the entire project duration
Short-term (commitment plan)Devised on a daily basis to register the assignment of tasks to crews on site
LearningDaily measurements of percent of plan complete (PPC) along with root cause analysis