LPS’s adaptations to suit the retrofit context (Kemmer et al., 2016)
| LPS element | Phase 1B |
|---|---|
| Long-term (master plan) | Devised in a collaborative fashion by the delivery team through the use of Post-it notes and a location-based chart |
| Phase planning | |
| Medium-term (look-ahead plan) | Constraints were listed for the entire project duration |
| Short-term (commitment plan) | Devised on a daily basis to register the assignment of tasks to crews on site |
| Learning | Daily measurements of percent of plan complete (PPC) along with root cause analysis |
| LPS element | Phase 1B |
|---|---|
| Long-term (master plan) | Devised in a collaborative fashion by the delivery team through the use of Post-it notes and a location-based chart |
| Phase planning | |
| Medium-term (look-ahead plan) | Constraints were listed for the entire project duration |
| Short-term (commitment plan) | Devised on a daily basis to register the assignment of tasks to crews on site |
| Learning | Daily measurements of percent of plan complete (PPC) along with root cause analysis |