Table 4

Scenarios developed for 4D simulation in phase 2

ScenarioHouse numberTotal duration: dRed disruptions: dOrange disruptions: dNumber of disruptions/house: dNumber of disruptions/scenario: dWIP: dNumber of workers
146196162241529
47207121941399
246219142341667
47218101841347
346217152242608
47227132042378

Scenario 1 was considered to be the most effective, as it results in the shortest duration and smaller number of disruptive days. However, the option requires a larger number of workers on site