Regressions results on the relationships between study variables
| Variables and effects | Procurement performance | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Cost reduction | Lead times | Buyer satisfaction | ||||||||||
| Coeff | se | t | p | Coeff | se | t | p | Coeff | se | t | p | |
| Supplier monitoring | 0.2867 | 0.0566 | 5.0685 | **** | 0.3577 | 0.0573 | 6.2415 | **** | 0.3575 | 0.0553 | 6.4587 | **** |
| Contract management difficulty | 0.1955 | 0.0619 | 3.1598 | 0.0019 | 0.1158 | 0.0627 | 1.8474 | 0.0664 | 0.0630 | 0.0606 | 1.0412 | 0.2992 |
| Int_1 | −0.1082 | 0.0489 | −2.2150 | 0.0281 | −0.1731 | 0.0495 | −3.4961 | 0.0006 | −0.1128 | 0.0478 | −2.3581 | 0.0195 |
| R2 | 0.2773 | **** | 0.3343 | **** | 0.2926 | **** | ||||||
| ΔR2 | 0.0203 | 0.0465 | 0.0225 | |||||||||
| Variables and effects | Procurement performance | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Cost reduction | Lead times | Buyer satisfaction | ||||||||||
| Coeff | se | Coeff | se | Coeff | se | |||||||
| Supplier monitoring | 0.2867 | 0.0566 | 5.0685 | **** | 0.3577 | 0.0573 | 6.2415 | **** | 0.3575 | 0.0553 | 6.4587 | **** |
| Contract management difficulty | 0.1955 | 0.0619 | 3.1598 | 0.0019 | 0.1158 | 0.0627 | 1.8474 | 0.0664 | 0.0630 | 0.0606 | 1.0412 | 0.2992 |
| Int_1 | −0.1082 | 0.0489 | −2.2150 | 0.0281 | −0.1731 | 0.0495 | −3.4961 | 0.0006 | −0.1128 | 0.0478 | −2.3581 | 0.0195 |
| 0.2773 | **** | 0.3343 | **** | 0.2926 | **** | |||||||
| Δ | 0.0203 | 0.0465 | 0.0225 | |||||||||
Note(s): Int_1 denotes Contract management difficulty*Supplier monitoring
**** denotes p < 0.01