Foundations with connected turbines to the grid in 2018 in the European offshore wind sector (WindEurope, 2019).
| Wind Farm | Connected capacity in 2018 (MW) | No. of turbines connected in 2018 | Type of Foundation |
|---|---|---|---|
| Walney Extension Phase East | 329 | 47 | Bottom-fixed |
| Galloper | 277·2 | 44 | Bottom-fixed |
| Beatrice | 273 | 39 | Bottom-fixed |
| Rampion | 220·8 | 64 | Bottom-fixed |
| EOWDC | 93·2 | 11 | Bottom-fixed |
| Walney Extension Phase West | 66 | 8 | Bottom-fixed |
| Race Bank | 50·4 | 8 | Bottom-fixed |
| Kincardine Pilot | 2 | 1 | Floating |
| Borkum Riffgrund II | 464·8 | 56 | Bottom-fixed |
| Arkona | 384 | 60 | Bottom-fixed |
| Merkur Offshore | 120 | 20 | Bottom-fixed |
| Rentel | 308·7 | 42 | Bottom-fixed |
| Horns Rev 3 | 33·2 | 4 | Bottom-fixed |
| Nissum Bredning | 28 | 4 | Bottom-fixed |
| Elisa Elican | 5 | 1 | Bottom-fixed |
| Blockstigen | 3·3 | 5 | Bottom-fixed |
| Floatgen | 2 | 1 | Floating |
| Eolink Prototype | 0·2 | 1 | Floating |
| Total amount | 2660·8 | 416 | – |
| Walney Extension Phase East | 329 | 47 | Bottom-fixed |
| Galloper | 277·2 | 44 | Bottom-fixed |
| Beatrice | 273 | 39 | Bottom-fixed |
| Rampion | 220·8 | 64 | Bottom-fixed |
| EOWDC | 93·2 | 11 | Bottom-fixed |
| Walney Extension Phase West | 66 | 8 | Bottom-fixed |
| Race Bank | 50·4 | 8 | Bottom-fixed |
| Kincardine Pilot | 2 | 1 | Floating |
| Borkum Riffgrund II | 464·8 | 56 | Bottom-fixed |
| Arkona | 384 | 60 | Bottom-fixed |
| Merkur Offshore | 120 | 20 | Bottom-fixed |
| Rentel | 308·7 | 42 | Bottom-fixed |
| Horns Rev 3 | 33·2 | 4 | Bottom-fixed |
| Nissum Bredning | 28 | 4 | Bottom-fixed |
| Elisa Elican | 5 | 1 | Bottom-fixed |
| Blockstigen | 3·3 | 5 | Bottom-fixed |
| Floatgen | 2 | 1 | Floating |
| Eolink Prototype | 0·2 | 1 | Floating |
| Total amount | 2660·8 | 416 | – |