Table 3.

IPD Contractual, behavioral and supporting elements implemented at the Tønsberg project

Implemented elements of IPDTønsberg project
Contract 
A    Early involvement of key participantsImplemented
B    Shared risk and rewardImplemented
C    Joint project controlImplemented
D    Reduced liability exposurePartly implemented
E    Multiparty agreementsImplemented
F    Jointly developed and validated targetsImplemented
G    Fiscal transparencyPartly implemented
H    Intensified design and planningImplemented
Behavior 
A    Respect and trustImplemented
B    Willingness to collaborateImplemented
C    Open communicationImplemented
Co-locationImplemented
Lean constructionImplemented
BIMImplemented