Precedence network of the activities
| ID | Task identification | Precedence | Duration (h) |
|---|---|---|---|
| 1 | 1. Receiving and operational tests | 21.3 | |
| 2 | 1.1 Loose items removal | 4 | |
| 3 | 1.2 Mechanics receiving and operational tests | 2 | 2.7 |
| 4 | 1.3 Avionics receiving and operational tests (data collection) | 2 | 11.85 |
| 5 | 1.4 Composite material receiving | 2 | 2 |
| 6 | 1.5 Structure receiving | 2 | 5 |
| 7 | 1.6 Painting receiving | 2 | 4 |
| 8 | 1.7 Interior receiving | 2 | 5 |
| 9 | 1.8 QTU/QTA (reservoir drain) | 8 | 1.5 |
| 10 | 1.9 Engine run | 6; 3; 7; 5; 9 | 2 |
| 11 | 1.10 Opening of discrepancy documents | 3; 4; 5; 6; 7; 8; 12 | 1.5 |
| 12 | 1.11 Troubleshooting | 10 | 4 |
| 13 | 1.12 Fuel test | 0.8 | |
| 14 | 1.13 Compressor washing | 10; 13 | 3 |
| 15 | 1.14 Landing gear washing | 10; 13 | 4 |
| 16 | 1.15 Defueling | 13; 15; 14; 11 | 1.5 |
| 17 | 2. Hangaring and access openings | 1 | 18 |
| 18 | 2.1 Hangaring | 16 | 1 |
| 19 | 2.2 Wing edge protection installation | 18 | 0.5 |
| 20 | 2.3 Furniture protection installation | 18 | 2 |
| 21 | 2.4 Internal access openings | 19; 20 | 12 |
| 22 | 2.5 External access openings | 19; 20 | 15 |
| 23 | 3. Operational checks and component removals | 17 | 11 |
| 24 | 3.1 Electric hangar check | 18 | 2.1 |
| 25 | 3.2 Removal/ship components to workshop | 21; 24; 22 | 1 |
| 26 | 3.3 Lubrification | 22 | 1.8 |
| 27 | 3.4 Engine and air conditioning routines | 21; 22 | 4.5 |
| 28 | 3.5 Electric routine | 21; 22 | 0.5 |
| 29 | 3.6 Interior routine | 18 | 3 |
| 30 | 3.7 Inspection (sealing/films) | 18 | 0.3 |
| 31 | 3.8 Out-of-phase | 21; 22 | 11 |
| 32 | 4. Discrepancy correction | 23 | 28 |
| 33 | 4.1 Discrepancy – mechanics | 21; 22 | 28 |
| 34 | 4.2 Discrepancy – avionics | 21; 22 | 18 |
| 35 | 4.3 Discrepancy – painting | 18 | 14 |
| 36 | 4.4 Discrepancy – sealing | 18 | 12 |
| 37 | 4.5 Discrepancy – interior | 21; 22 | 10 |
| 38 | 4.6 Discrepancy – structure | 21; 22 | 7 |
| 39 | 4.7 Client’s reports – interior | 21 | 17 |
| 40 | 4.8 Client's reports – avionics | 21; 22 | 10 |
| 41 | 4.9 Client's reports – mechanics | 21; 22 | 6 |
| 42 | 4.10 Client's reports – painting and sealing | 18 | 7 |
| 43 | 5. Components installation and accesses closing | 32 | 54 |
| 44 | 5.1 Installation of repaired components | 25 | 1 |
| 45 | 5.2 Components operational tests | 44 | 4 |
| 46 | 5.3 Internal accesses closing | 44II | 30 |
| 47 | 5.4 External accesses closing | 44II | 36 |
| 48 | 5.5 Sealant application | 47TT+1 hrd | 12 |
| 49 | 5.6 Painting of sealing threads | 48 | 15 |
| 50 | 5.7 Wing edge and furniture protections removal | 49 | 1 |
| 51 | 5.8 Taxiing aircraft to courtyard | 50 | 1 |
| 52 | 6. Pre-flight and Final Inspections | 43 | 19.85 |
| 53 | 6.1 Fueling | 1 | |
| 54 | 6.2 Engine run | 53 | 2 |
| 55 | 6.3 Final inspection – mechanics | 54 | 2 |
| 56 | 6.4 Final inspection – avionics | 54 | 4 |
| 57 | 6.5 Final inspection – Interior | 54 | 5 |
| 58 | 6.6 Corrections post final inspection | 55; 56; 57 | 5.85 |
| 59 | 6.7 QTU/QTA | 57 | 1.5 |
| 60 | 6.8 Dry clean (internal and external) | 59; 58 | 4 |
| 61 | 6.9 Pre-flight procedure | 60 | 2 |
| 62 | 6.10 Prepare release and documentation | 58 | 5 |
| 63 | 7. Aircraft delivery | 52 | 7 |
| 64 | 7.1 Customer delivery | 61 | 5 |
| 65 | 7.2 Maintenance flight | 64 | 2 |
| ID | Task identification | Precedence | Duration (h) |
|---|---|---|---|
| 1 | |||
| 2 | 1.1 Loose items removal | 4 | |
| 3 | 1.2 Mechanics receiving and operational tests | 2 | 2.7 |
| 4 | 1.3 Avionics receiving and operational tests (data collection) | 2 | 11.85 |
| 5 | 1.4 Composite material receiving | 2 | 2 |
| 6 | 1.5 Structure receiving | 2 | 5 |
| 7 | 1.6 Painting receiving | 2 | 4 |
| 8 | 1.7 Interior receiving | 2 | 5 |
| 9 | 1.8 QTU/QTA (reservoir drain) | 8 | 1.5 |
| 10 | 1.9 Engine run | 6; 3; 7; 5; 9 | 2 |
| 11 | 1.10 Opening of discrepancy documents | 3; 4; 5; 6; 7; 8; 12 | 1.5 |
| 12 | 1.11 Troubleshooting | 10 | 4 |
| 13 | 1.12 Fuel test | 0.8 | |
| 14 | 1.13 Compressor washing | 10; 13 | 3 |
| 15 | 1.14 Landing gear washing | 10; 13 | 4 |
| 16 | 1.15 Defueling | 13; 15; 14; 11 | 1.5 |
| 17 | |||
| 18 | 2.1 Hangaring | 16 | 1 |
| 19 | 2.2 Wing edge protection installation | 18 | 0.5 |
| 20 | 2.3 Furniture protection installation | 18 | 2 |
| 21 | 2.4 Internal access openings | 19; 20 | 12 |
| 22 | 2.5 External access openings | 19; 20 | 15 |
| 23 | |||
| 24 | 3.1 Electric hangar check | 18 | 2.1 |
| 25 | 3.2 Removal/ship components to workshop | 21; 24; 22 | 1 |
| 26 | 3.3 Lubrification | 22 | 1.8 |
| 27 | 3.4 Engine and air conditioning routines | 21; 22 | 4.5 |
| 28 | 3.5 Electric routine | 21; 22 | 0.5 |
| 29 | 3.6 Interior routine | 18 | 3 |
| 30 | 3.7 Inspection (sealing/films) | 18 | 0.3 |
| 31 | 3.8 Out-of-phase | 21; 22 | 11 |
| 32 | |||
| 33 | 4.1 Discrepancy – mechanics | 21; 22 | 28 |
| 34 | 4.2 Discrepancy – avionics | 21; 22 | 18 |
| 35 | 4.3 Discrepancy – painting | 18 | 14 |
| 36 | 4.4 Discrepancy – sealing | 18 | 12 |
| 37 | 4.5 Discrepancy – interior | 21; 22 | 10 |
| 38 | 4.6 Discrepancy – structure | 21; 22 | 7 |
| 39 | 4.7 Client’s reports – interior | 21 | 17 |
| 40 | 4.8 Client's reports – avionics | 21; 22 | 10 |
| 41 | 4.9 Client's reports – mechanics | 21; 22 | 6 |
| 42 | 4.10 Client's reports – painting and sealing | 18 | 7 |
| 43 | |||
| 44 | 5.1 Installation of repaired components | 25 | 1 |
| 45 | 5.2 Components operational tests | 44 | 4 |
| 46 | 5.3 Internal accesses closing | 44II | 30 |
| 47 | 5.4 External accesses closing | 44II | 36 |
| 48 | 5.5 Sealant application | 47TT+1 hrd | 12 |
| 49 | 5.6 Painting of sealing threads | 48 | 15 |
| 50 | 5.7 Wing edge and furniture protections removal | 49 | 1 |
| 51 | 5.8 Taxiing aircraft to courtyard | 50 | 1 |
| 52 | |||
| 53 | 6.1 Fueling | 1 | |
| 54 | 6.2 Engine run | 53 | 2 |
| 55 | 6.3 Final inspection – mechanics | 54 | 2 |
| 56 | 6.4 Final inspection – avionics | 54 | 4 |
| 57 | 6.5 Final inspection – Interior | 54 | 5 |
| 58 | 6.6 Corrections post final inspection | 55; 56; 57 | 5.85 |
| 59 | 6.7 QTU/QTA | 57 | 1.5 |
| 60 | 6.8 Dry clean (internal and external) | 59; 58 | 4 |
| 61 | 6.9 Pre-flight procedure | 60 | 2 |
| 62 | 6.10 Prepare release and documentation | 58 | 5 |
| 63 | |||
| 64 | 7.1 Customer delivery | 61 | 5 |
| 65 | 7.2 Maintenance flight | 64 | 2 |