Table 2

Initial estimation and actual construction cost and time of study highway project

StructureCost: ZARTime: days
Initial estimation (deterministic)ActualInitial estimation (deterministic)Actual
Earthwork244 292 292.83410 415 938.89215431
Bridge70 952 700.0096 543 919.84340539
Pavement494 259 930.00657 775 942.64217320
Overall project809 504 922.801 164 735 801.37340539

1 ZAR = 0.053 GBP in 2016