Correlation costs and times
| Structure | Correlation | Cost | Time | ||||
|---|---|---|---|---|---|---|---|
| Mean | P90th | P90th: increased % | Mean | P90th | P90th: increased % | ||
| Earthwork | Base case | 268 726 606.90 | 271 089 094.40 | 10.97 | 222.19 | 225.59 | 4.93 |
| Type 1 | 268 692 562.60 | 286 766 429.79 | 17.39 | 222.19 | 249.18 | 15.90 | |
| Type 2 | 268 608 078.40 | 298 968 508.46 | 22.38 | 222.32 | 253.63 | 17.97 | |
| Type 3 | 268 530 325.90 | 292 373 016.20 | 19.68 | 222.78 | 254.45 | 18.35 | |
| Bridge | Base case | 78 030 393.34 | 80 577 949.52 | 13.57 | 351.35 | 357.78 | 5.23 |
| Type 1 | 78 044 588.91 | 85 920 760.74 | 21.10 | 351.36 | 396.52 | 16.62 | |
| Type 2 | 78 113 067.80 | 86 205 928.64 | 21.50 | 351.46 | 392.89 | 15.56 | |
| Type 3 | 78 065 388.98 | 86 085 866.87 | 21.33 | 349.72 | 381.19 | 12.12 | |
| Pavement | Base case | 543 664 957.99 | 548 997 579.66 | 11.07 | 224.22 | 227.62 | 4.90 |
| Type 1 | 543 716 702.76 | 588 988 971.85 | 19.17 | 224.28 | 239.00 | 10.14 | |
| Type 2 | 543 899 815.54 | 612 440 433.36 | 23.91 | 224.41 | 241.64 | 11.35 | |
| Type 3 | 543 558 761.37 | 596 935 711.88 | 20.77 | 224.24 | 239.16 | 10.21 | |
| Overall project | Base case | 821 606 531.66 | 896 942 973.77 | 10.80 | 341.54 | 357.67 | 5.20 |
| Type 1 | 889 994 457.90 | 939 759 672.15 | 16.09 | 351.45 | 395.32 | 16.27 | |
| Type 2 | 889 203 018.70 | 962 076 539.65 | 18.85 | 351.23 | 392.52 | 15.45 | |
| Type 3 | 892 317 669.00 | 949 067 831.41 | 17.24 | 351.23 | 381.25 | 12.13 | |
| Structure | Correlation | Cost | Time | ||||
|---|---|---|---|---|---|---|---|
| Mean | P90th | P90th: increased % | Mean | P90th | P90th: increased % | ||
| Earthwork | Base case | 268 726 606.90 | 271 089 094.40 | 10.97 | 222.19 | 225.59 | 4.93 |
| Type 1 | 268 692 562.60 | 286 766 429.79 | 17.39 | 222.19 | 249.18 | 15.90 | |
| Type 2 | 268 608 078.40 | 298 968 508.46 | 22.38 | 222.32 | 253.63 | 17.97 | |
| Type 3 | 268 530 325.90 | 292 373 016.20 | 19.68 | 222.78 | 254.45 | 18.35 | |
| Bridge | Base case | 78 030 393.34 | 80 577 949.52 | 13.57 | 351.35 | 357.78 | 5.23 |
| Type 1 | 78 044 588.91 | 85 920 760.74 | 21.10 | 351.36 | 396.52 | 16.62 | |
| Type 2 | 78 113 067.80 | 86 205 928.64 | 21.50 | 351.46 | 392.89 | 15.56 | |
| Type 3 | 78 065 388.98 | 86 085 866.87 | 21.33 | 349.72 | 381.19 | 12.12 | |
| Pavement | Base case | 543 664 957.99 | 548 997 579.66 | 11.07 | 224.22 | 227.62 | 4.90 |
| Type 1 | 543 716 702.76 | 588 988 971.85 | 19.17 | 224.28 | 239.00 | 10.14 | |
| Type 2 | 543 899 815.54 | 612 440 433.36 | 23.91 | 224.41 | 241.64 | 11.35 | |
| Type 3 | 543 558 761.37 | 596 935 711.88 | 20.77 | 224.24 | 239.16 | 10.21 | |
| Overall project | Base case | 821 606 531.66 | 896 942 973.77 | 10.80 | 341.54 | 357.67 | 5.20 |
| Type 1 | 889 994 457.90 | 939 759 672.15 | 16.09 | 351.45 | 395.32 | 16.27 | |
| Type 2 | 889 203 018.70 | 962 076 539.65 | 18.85 | 351.23 | 392.52 | 15.45 | |
| Type 3 | 892 317 669.00 | 949 067 831.41 | 17.24 | 351.23 | 381.25 | 12.13 | |
Base case: uncorrelated (variability cost and time)
Type 1: correlation between repeated activities in a structure
Type 2: correlation between activities in a structure
Type 3: correlation between cost and time of an activity