Table 4

Correlation costs and times

StructureCorrelationCostTime
MeanP90thP90th: increased %MeanP90thP90th: increased %
EarthworkBase case268 726 606.90271 089 094.4010.97222.19225.594.93
Type 1268 692 562.60286 766 429.7917.39222.19249.1815.90
Type 2268 608 078.40298 968 508.4622.38222.32253.6317.97
Type 3268 530 325.90292 373 016.2019.68222.78254.4518.35
BridgeBase case78 030 393.3480 577 949.5213.57351.35357.785.23
Type 178 044 588.9185 920 760.7421.10351.36396.5216.62
Type 278 113 067.8086 205 928.6421.50351.46392.8915.56
Type 378 065 388.9886 085 866.8721.33349.72381.1912.12
PavementBase case543 664 957.99548 997 579.6611.07224.22227.624.90
Type 1543 716 702.76588 988 971.8519.17224.28239.0010.14
Type 2543 899 815.54612 440 433.3623.91224.41241.6411.35
Type 3543 558 761.37596 935 711.8820.77224.24239.1610.21
Overall projectBase case821 606 531.66896 942 973.7710.80341.54357.675.20
Type 1889 994 457.90939 759 672.1516.09351.45395.3216.27
Type 2889 203 018.70962 076 539.6518.85351.23392.5215.45
Type 3892 317 669.00949 067 831.4117.24351.23381.2512.13

Base case: uncorrelated (variability cost and time)

Type 1: correlation between repeated activities in a structure

Type 2: correlation between activities in a structure

Type 3: correlation between cost and time of an activity