Table 6

Impact of uncertainty on the construction cost and time of the case study

StructureUncertainty sourceCostTime
DeterministicP90thP90th: increased %DeterministicP90thP90th: increased %
EarthworkVariability244 292 292.83258 410 039.215.78215228.766.40
Variability and correlation298 968 508.4622.38254.4518.35
Variability, correlation and disruptive events407 968 130.1167.00425.798.00
 
BridgeVariability70 952 700.0076 883 575.678.36340369.488.67
Variability and correlation86 205 928.6421.50396.5216.62
Variability, correlation and disruptive events97 914 726.0038.00544.0060.00
 
PavementVariability494 259 930.00517 582 030.414.72217228.535.31
Variability and correlation612 440 433.3623.91241.6411.35
Variability, correlation and disruptive events667 250 905.5035.00323.3349.00
 
Overall projectVariability809 504 922.8841 927 264.184.01340368.648.42
Variability and correlation962 076 539.6518.85395.3216.27
Variability, correlation and disruptive events1 154 839 722.8742.66544.0060.00