The tasks, associated resources and efficiencies in DES model
| Task name | Resource: Equipment (R1)/worker (R2) | Unit | Efficiency | |
|---|---|---|---|---|
| PC external wall hoist | Crane (STT293) | PC worker | min/pcs | Uniform(20.3, 22.3)† |
| PC internal wall hoist | Crane (STT293) | PC worker | min/pcs | Uniform(20.3, 22.3)† |
| PC wall support install | Crane (STT293) | min/pcs | Uniform(5.8, 9)† | |
| Installation adjust | PC worker | min/pcs | P{20} = 20% P{0} = 80%† | |
| Joint grout | Rebar install worker | min/pcs | 15.024* | |
| PC beam hoist | Crane (STT293) | PC worker | min/pcs | Uniform(20.3, 22.3)† |
| PC slab hoist | Crane (STT293) | PC worker | min/pcs | Uniform(20.3, 22.3)† |
| PC stair hoist | Crane (STT293) | PC worker | min/pcs | Uniform(20.3, 22.3)† |
| PC balcony hoist | Crane (STT293) | PC worker | min/pcs | Uniform(20.3, 22.3)† |
| PC beam support | Crane (STT293) | min/pcs | Uniform(5.8, 9)† | |
| PC slab support install | Crane (STT293) | min/pcs | Uniform(5.8, 9)† | |
| PC wall transportation | Wall truck | min/batch | Uniform(100, 120)† | |
| PC beam transportation | Beam truck | min/batch | Uniform(100, 120)† | |
| PC slab transportation | Slab truck | min/batch | Uniform(100, 120)† | |
| PC stairs and balcony transportation | Stairs and balcony truck | min/batch | Uniform(100, 120)† | |
| PC wall unload | Crane (STT293) | Wall truck | min/pcs | Uniform(7.3, 9.3)† |
| PC beam unload | Crane (STT293) | Beam truck | min/pcs | Uniform(7.3, 9.3)† |
| PC slab unload | Crane (STT293) | Slab truck | min/pcs | Uniform(7.3, 9.3)† |
| PC stairs and balcony unload | Crane (STT293) | Stairs and balcony truck | min/pcs | Uniform(7.3, 9.3)† |
| CS concrete pump | Pump | Concrete worker | m3/h | 70 |
| CS beam and slab rebar install | Rebar install worker | min/m2 | 10.04* | |
| CS wall and column rebar install | Rebar install worker | min/m2 | 11.63* | |
| Post pouring joint formwork install | Crane (STT293) | min/pcs | CS = Uniform(5.8, 9)† | |
| CS wall and column and beam formwork install | Formwork worker | min/m2 | 13.85* | |
| CS wall and column rebar processing | Rebar processing worker | min/m2 | 60.26* | |
| CS wall and column rebar transportation | Rebar processing worker | Lift | min/batch | (Uniform(1, 2) × ht./36 + 6)/4* |
| CS beam and slab rebar transportation | Rebar processing worker | Lift | min/batch | (Uniform(1, 2) × ht./36 + 6)/4* |
| Task name | Resource: Equipment ( | Unit | Efficiency | |
|---|---|---|---|---|
| PC external wall hoist | Crane (STT293) | PC worker | min/pcs | Uniform(20.3, 22.3)† |
| PC internal wall hoist | Crane (STT293) | PC worker | min/pcs | Uniform(20.3, 22.3)† |
| PC wall support install | Crane (STT293) | min/pcs | Uniform(5.8, 9)† | |
| Installation adjust | PC worker | min/pcs | P{20} = 20% | |
| Joint grout | Rebar install worker | min/pcs | 15.024* | |
| PC beam hoist | Crane (STT293) | PC worker | min/pcs | Uniform(20.3, 22.3)† |
| PC slab hoist | Crane (STT293) | PC worker | min/pcs | Uniform(20.3, 22.3)† |
| PC stair hoist | Crane (STT293) | PC worker | min/pcs | Uniform(20.3, 22.3)† |
| PC balcony hoist | Crane (STT293) | PC worker | min/pcs | Uniform(20.3, 22.3)† |
| PC beam support | Crane (STT293) | min/pcs | Uniform(5.8, 9)† | |
| PC slab support install | Crane (STT293) | min/pcs | Uniform(5.8, 9)† | |
| PC wall transportation | Wall truck | min/batch | Uniform(100, 120)† | |
| PC beam transportation | Beam truck | min/batch | Uniform(100, 120)† | |
| PC slab transportation | Slab truck | min/batch | Uniform(100, 120)† | |
| PC stairs and balcony transportation | Stairs and balcony truck | min/batch | Uniform(100, 120)† | |
| PC wall unload | Crane (STT293) | Wall truck | min/pcs | Uniform(7.3, 9.3)† |
| PC beam unload | Crane (STT293) | Beam truck | min/pcs | Uniform(7.3, 9.3)† |
| PC slab unload | Crane (STT293) | Slab truck | min/pcs | Uniform(7.3, 9.3)† |
| PC stairs and balcony unload | Crane (STT293) | Stairs and balcony truck | min/pcs | Uniform(7.3, 9.3)† |
| CS concrete pump | Pump | Concrete worker | m3/h | 70 |
| CS beam and slab rebar install | Rebar install worker | min/m2 | 10.04* | |
| CS wall and column rebar install | Rebar install worker | min/m2 | 11.63* | |
| Post pouring joint formwork install | Crane (STT293) | min/pcs | CS = Uniform(5.8, 9)† | |
| CS wall and column and beam formwork install | Formwork worker | min/m2 | 13.85* | |
| CS wall and column rebar processing | Rebar processing worker | min/m2 | 60.26* | |
| CS wall and column rebar transportation | Rebar processing worker | Lift | min/batch | (Uniform(1, 2) × ht./36 + 6)/4* |
| CS beam and slab rebar transportation | Rebar processing worker | Lift | min/batch | (Uniform(1, 2) × ht./36 + 6)/4* |
Note(s): * the value is calculated from local Construction Engineering Quota database (SCPCM, 2016a, 2016b), † the value is from on-site pre-experiments
Sharing content requires targeting cookies to be enabled. Please update your cookie preferences to use this feature.