The outcome of the simulation and the construction documents of a typical floor
| Testing item | Unit | Document quantities | Simulation |
|---|---|---|---|
| Cost of cranes | CNY | 965463.344 | 1,089,140 |
| Cost of construction lifts | CNY | 1405916.4 | 1,405,920 |
| Cost of concrete pumps | CNY | 502863.2 | 502,863 |
| Labour for CS beam and slab rebar process | CNY | 185584.042 | 185,584 |
| Labour for CS wall and column rebar process | CNY | 148282.393 | 148,282 |
| Labour for PC external wall hoist and installation | CNY | 1175755.03 | 1,175,760 |
| Labour for PC balcony hoist and installation | CNY | 91835.8134 | 91835.8 |
| Labour for PC internal wall hoist and installation | CNY | 292757.501 | 292,758 |
| Labour for CS concrete pump, vibration and curving | CNY | 997323.92 | 997,324 |
| Labour for PC slab hoist and installation | CNY | 412919.246 | 412,919 |
| Labour for PC beam hoist and installation | CNY | 140441.223 | 140,441 |
| Labour for PC stair hoist and installation | CNY | 123976.842 | 123,977 |
| Labour for CS wall and column rebar installation | CNY | 310161.014 | 310,161 |
| Labour for joint grout | CNY | 614074.102 | 614,074 |
| Labour for climbing formwork | CNY | 3,024,810 | 3,024,810 |
| Diesel consumption of PC trucks | kg | 50775.386 | 50775.4 |
| Power consumption of concrete pumps | kWh | 15025.5102 | 15,747 |
| Power consumption of cranes | kWh | 486,623 | 491,892 |
| Power consumption of construction lifts | kWh | 75113.775 | 75113.8 |
| Testing item | Unit | Document quantities | Simulation |
|---|---|---|---|
| Cost of cranes | CNY | 965463.344 | 1,089,140 |
| Cost of construction lifts | CNY | 1405916.4 | 1,405,920 |
| Cost of concrete pumps | CNY | 502863.2 | 502,863 |
| Labour for CS beam and slab rebar process | CNY | 185584.042 | 185,584 |
| Labour for CS wall and column rebar process | CNY | 148282.393 | 148,282 |
| Labour for PC external wall hoist and installation | CNY | 1175755.03 | 1,175,760 |
| Labour for PC balcony hoist and installation | CNY | 91835.8134 | 91835.8 |
| Labour for PC internal wall hoist and installation | CNY | 292757.501 | 292,758 |
| Labour for CS concrete pump, vibration and curving | CNY | 997323.92 | 997,324 |
| Labour for PC slab hoist and installation | CNY | 412919.246 | 412,919 |
| Labour for PC beam hoist and installation | CNY | 140441.223 | 140,441 |
| Labour for PC stair hoist and installation | CNY | 123976.842 | 123,977 |
| Labour for CS wall and column rebar installation | CNY | 310161.014 | 310,161 |
| Labour for joint grout | CNY | 614074.102 | 614,074 |
| Labour for climbing formwork | CNY | 3,024,810 | 3,024,810 |
| Diesel consumption of PC trucks | kg | 50775.386 | 50775.4 |
| Power consumption of concrete pumps | kWh | 15025.5102 | 15,747 |
| Power consumption of cranes | kWh | 486,623 | 491,892 |
| Power consumption of construction lifts | kWh | 75113.775 | 75113.8 |
Sharing content requires targeting cookies to be enabled. Please update your cookie preferences to use this feature.