Table A1

The outcome of the simulation and the construction documents of a typical floor

Testing itemUnitDocument quantitiesSimulation
Cost of cranesCNY965463.3441,089,140
Cost of construction liftsCNY1405916.41,405,920
Cost of concrete pumpsCNY502863.2502,863
Labour for CS beam and slab rebar processCNY185584.042185,584
Labour for CS wall and column rebar processCNY148282.393148,282
Labour for PC external wall hoist and installationCNY1175755.031,175,760
Labour for PC balcony hoist and installationCNY91835.813491835.8
Labour for PC internal wall hoist and installationCNY292757.501292,758
Labour for CS concrete pump, vibration and curvingCNY997323.92997,324
Labour for PC slab hoist and installationCNY412919.246412,919
Labour for PC beam hoist and installationCNY140441.223140,441
Labour for PC stair hoist and installationCNY123976.842123,977
Labour for CS wall and column rebar installationCNY310161.014310,161
Labour for joint groutCNY614074.102614,074
Labour for climbing formworkCNY3,024,8103,024,810
Diesel consumption of PC truckskg50775.38650775.4
Power consumption of concrete pumpskWh15025.510215,747
Power consumption of craneskWh486,623491,892
Power consumption of construction liftskWh75113.77575113.8