Findings and key quotes from Road B
| Road B | |
|---|---|
| Uncertainty |
|
| Equivocality |
|
| Road B | |
|---|---|
| Uncertainty | Road B did not receive all required information due to wrong configurations in the connection between their own system and their supplier's system and because of misunderstandings about what data were actually needed: [18] “ |
| Equivocality | The data in Road B's database did not have the correct data format and the extended time it takes to fix the data format rendered the data useless: [20] “ (2)Road B's system could not handle all types of file formats they received |
| Contractual Governance | Relational Governance | |
|---|---|---|
| Information Acquisition |
[24] “They do get a penalty, but that is sometimes much less than what they can save if they do nothing” – Asset Specialist 1
|
[29] “What does the supplier need and what do we need? That is how we collaborate. It is no longer about pointing fingers to each other” – Configuration Manager 1 [30] “Our goal now is to collaborate more with the market. Previously, we had a more steering role” – Contract Manager 2
|
| Information Transformation |
|
[35] “We look at the asset in the field. Is it properly maintained, and does it [information in the system] match the current state of the asset? And that you then assess together” – Contract Manager 2
|
| Contractual Governance | Relational Governance | |
|---|---|---|
| Information Acquisition | Contracts stipulated that Road owned the data. Suppliers had to share to avoid penalties (i.e. control); penalties were found to be ineffective (2) Contracts also included the requirement to connect data systems (control) (3) Agreements about what to share were vague and inconsistent (coordination) | Suppliers seemed hesitant to share all maintenance data (2) Road invested in open communication and tried to refrain from penalising suppliers immediately to avoid a blaming game (3) Road sought to enhance current relationships through two-way sharing |
| Information Transformation | Misaligned contract agreements hampered transformation (2)Contract stipulated that recurring meetings should have been organised to jointly interpret and transform information | Road sought collaboration to receive all information (2)Closer collaboration was also needed to induce flexibility and motivate parties to look beyond contract agreements |