Summary of research case megaprojects
| Characteristics | Case A | Case B | Case C | Case D | Case E | Case F |
|---|---|---|---|---|---|---|
| Buyer | Private-owned | State-owned | State-owned-led EJV | Private-owned | Private-owned | State-owned |
| Infrastructure type | Independent power plant | Energy/utility plant | Energy/utility plant | Independent power plant | Independent power plant | Energy/utility plant |
| EM | Bangladesh | Indonesia | Brazil | Jordan | Pakistan | Indonesia |
| Host market regulations for energy infrastructure | Limited competition, major influence of government | Limited competition, major influence of government | Fairly liberalized, limited influence of government | Limited competition, major influence of government | Moderate competition, noticeable influence of government | Limited competition, major influence of government |
| Energy Co.’s presence in country | +10 years | +10 years | +10 years | 0 years | +10 years | +10 years |
| Network office in host county | Yes | Yes | Yes | No | Yes | Yes |
| Project CAPEX | > US$150m | > US$150m | > US$250m | > US$200m | > US$150m | > US$150m |
| Payment method | Fixed price | Fixed price | Fixed price | Fixed price | Fixed price | Fixed price |
| Project procurement method | Solution supply and commissioning | Build–transfer (through JV) | Build–transfer | Build–transfer | Build–transfer–operate | Build–transfer |
| Duration | +1 years | +2 years | +2 years | +3 years | +3 years | +1 years |
| Project completion | 2017 | 2015 | 2013 | 2014 | 2012 | 2015 |
| Characteristics | Case A | Case B | Case C | Case D | Case E | Case F |
|---|---|---|---|---|---|---|
| Buyer | Private-owned | State-owned | State-owned-led EJV | Private-owned | Private-owned | State-owned |
| Infrastructure type | Independent power plant | Energy/utility plant | Energy/utility plant | Independent power plant | Independent power plant | Energy/utility plant |
| EM | Bangladesh | Indonesia | Brazil | Jordan | Pakistan | Indonesia |
| Host market regulations for energy infrastructure | Limited competition, major influence of government | Limited competition, major influence of government | Fairly liberalized, limited influence of government | Limited competition, major influence of government | Moderate competition, noticeable influence of government | Limited competition, major influence of government |
| Energy Co.’s presence in country | +10 years | +10 years | +10 years | 0 years | +10 years | +10 years |
| Network office in host county | Yes | Yes | Yes | No | Yes | Yes |
| Project CAPEX | > US$150m | > US$150m | > US$250m | > US$200m | > US$150m | > US$150m |
| Payment method | Fixed price | Fixed price | Fixed price | Fixed price | Fixed price | Fixed price |
| Project procurement method | Solution supply and commissioning | Build–transfer (through JV) | Build–transfer | Build–transfer | Build–transfer–operate | Build–transfer |
| Duration | +1 years | +2 years | +2 years | +3 years | +3 years | +1 years |
| Project completion | 2017 | 2015 | 2013 | 2014 | 2012 | 2015 |