Table 1

Successful factors to delivery GB projects

Relevant project activitiesSuccessful factorsSources
Planning activitiesInterdisciplinary interaction of project participants to gain an earlier and more comprehensive perception of project requirements for planning purposeIsa et al. (2014), Hwang et al. (2015) 
Organization activitiesThe owners' strong motivation and commitments on green buildingIsa et al. (2014), Hwang et al. (2015) 
Organization activitiesIntegrating the construction team into the project team is extremely criticalHwang et al. (2015), Swarup et al. (2011) 
Organization activitiesCapacity of change management to effectively solve emerging issues related to schedule, cost, quality and environment during the process of GB project deliveryIsa et al. (2014), Horman et al. (2006) 
Organization activitiesGB project participants need to continuously improve their knowledge of, expertise and readiness on green buildingIsa et al. (2014), Li et al. (2011), Horman et al. (2006) 
Onsite management and control activitiesMore communications and information sharing to limit conflicts among project participantsSwarup et al. (2011), Hwang et al. (2015) 
Onsite management and control activitiesActive and full collaboration and cooperation among all the relevant stakeholders to successfully incorporate innovative and advanced building technologies into the building systemsLi et al. (2011), Horman et al. (2006) 
Onsite management and control activitiesProvision of explicit and comprehensive green building codes and regulationsIsa et al. (2014), Li et al. (2011) 
Green supply chain activitiesReadiness of reliable green building technologies, products, materialsIsa et al. (2014), Hwang et al. (2015) 