Excerpt of the As-Is format of maintenance jobs used in scheduling. Some columns, such as dates, material requirements, and drop-off points, are excluded from this excerpt
| Order | Location | Equipment Type | Activity Number | Operation | Skills | Employees [#] | Planned work [h] |
|---|---|---|---|---|---|---|---|
A | A.1 | Pump | 1 | Isolate pump from production | Production | 2 | 2 |
2 | Remove current pump A.1 and replace with new pump XBPU1895 | Mechanics | 1 | 5 | |||
3 | De-Isolate | Production | 2 | 2 | |||
4 | Do test of new pump | Mechanics | 1 | 1 | |||
5 | Document pump replacement in master data | Mechanics | 1 | 1 | |||
B | A.2 | Pump motor | 1 | Safe pump + motor | Production | 2 | 2 |
2 | Do Function Test of motor | Mechanics | 1 | 3 | |||
3 | De-safe motor + pump | Production | 2 | 2 | |||
4 | Document test results in master data | Mechanics | 1 | 1 | |||
C | B.1 | Emergency Valve | 1 | Erect scaffold to reach valve | Scaf-team | 2 | 12 |
2 | Isolate | Production | 2 | 2 | |||
3 | Clean up the valve | Mechanics | 1 | 3 | |||
4 | De-Isolate | Production | 2 | 2 | |||
5 | Remove scaffold | Scaf-team | 2 | 6 | |||
6 | Document maintenance | Mechanics | 1 | 1 | |||
D | B.2 | Vessel | 1 | Build scaffold | Scaf-team | 2 | 12 |
2 | Function Test of the vessel | Mechanics | 1 | 8 | |||
3 | Document | Mechanics | 1 | 1 | |||
4 | Take down the scaff | Scaf-team | 2 | 6 |
| Order | Location | Equipment Type | Activity Number | Operation | Skills | Employees [#] | Planned work [h] |
|---|---|---|---|---|---|---|---|
A | A.1 | Pump | 1 | Isolate pump from production | Production | 2 | 2 |
2 | Remove current pump A.1 and replace with new pump XBPU1895 | Mechanics | 1 | 5 | |||
3 | De-Isolate | Production | 2 | 2 | |||
4 | Do test of new pump | Mechanics | 1 | 1 | |||
5 | Document pump replacement in master data | Mechanics | 1 | 1 | |||
B | A.2 | Pump motor | 1 | Safe pump + motor | Production | 2 | 2 |
2 | Do Function Test of motor | Mechanics | 1 | 3 | |||
3 | De-safe motor + pump | Production | 2 | 2 | |||
4 | Document test results in master data | Mechanics | 1 | 1 | |||
C | B.1 | Emergency Valve | 1 | Erect scaffold to reach valve | Scaf-team | 2 | 12 |
2 | Isolate | Production | 2 | 2 | |||
3 | Clean up the valve | Mechanics | 1 | 3 | |||
4 | De-Isolate | Production | 2 | 2 | |||
5 | Remove scaffold | Scaf-team | 2 | 6 | |||
6 | Document maintenance | Mechanics | 1 | 1 | |||
D | B.2 | Vessel | 1 | Build scaffold | Scaf-team | 2 | 12 |
2 | Function Test of the vessel | Mechanics | 1 | 8 | |||
3 | Document | Mechanics | 1 | 1 | |||
4 | Take down the scaff | Scaf-team | 2 | 6 |