Table I.

Numerical data

ParameterValue
Planning horizon2 weeks
Number of berths at the MCT: [BC1; BC2; BC3][2; 3; 4]
Vessel interarrival patterns − exponential: [A1; A2; A3; A4] (hours)[2.0; 2.3; 2.7; 3.0]
Containers assigned to each vessel: NCv,v ∈ V (TEUs)U [500; 2,000]
Handling productivity at the preferred berth: hpvb,v ∈ V,b ∈ B (TEUs per hour)125
Requested vessel departure: RDv,v ∈ V (hours)RDv = Av + HTvb · U[1.0; 1.2]
Vessel handling cost: cvH,vV (US$ per TEU)U [400; 600]
Vessel waiting cost: cvWT,vV (US$ per hour)U [1,500; 2,500]
Early departure premium: cvED,vV (US$ per hour)U [4,000; 6,000]
Late departure penalty: cvLD,vV (US$ per hour)U [6,000; 8,000]