Table AI

Summary of collected answers

QuestionCase 1Case 2Case 3
How the activities of the design stage are planned and controlled?Short meeting between the owner and the responsible engineer. Delays are commonMeeting between teams leaders of each area. A WBS and a detailed schedule are developed. The schedule is controlled every 15 days. Delays are commonMeeting involving in-house and subcontracted designers. A WBS and a simple schedule are developed. The schedule is controlled every 15 days. Delays are common
How definitions and technical decisions are made during design process?Engineer defines everything by himself, with the owner intervening only in complex cases. Clients are not involved because “they are not technically familiarized with the subject”Each has total autonomy to make technical decisions about its specialty. Errors in this definition process are source of constant and common reworksSubcontracted designers submit their technical decisions for approval of the specialty expert. There is no subcontracted integration. Erroneous decisions are only realized at the end and reworks are constantly needed
How is the client involved during the process?The client is not involved. Only receives the final designConstant and long validation meetings with the client’s designers to approve every decision point. The process is reported to be long and slow pacedClients biweekly validate the progress. Future executors (contractors) are also invited to evaluate the design at the end
How does development process flow between the teams and the employees? (Focus on authorities and responsibilities)Responsible engineer handles the whole development process, with the help of internsIt is a functional organization structure. Areas have full authority under its specialty. Integration between areas is always made through formal hierarchySubcontracteds rarely speak among themselves directly. All the communications are made through the project manager (reported to be a slow and bureaucratic process)
How the progress of the projects is reported to the in-house team and for the clients?With clients: e-mails/calls (not in a structured way)
Internal: verbally
With clients: technical meetings and monthly boards with mangers from both sides
Internal: periodic meetings involving department leaders only
With clients: technical meetings and semi-monthly boards with managers from both sides
Clients: verbally (little integration reported)
Was the current process reviewed in the past? Is there a plan for any change in the future?It always worked this way and there are no plans for changeThe process was defined after the merge process. Political barriers prevent revisionsDue to constant reworks in the past, the client was more involved. The intend to further improve the process, although it will be no radical change
There are problems with your products after your deliver it?Some problems in the execution phase. Clients sometimes complain of high costs due to allegedly over-design. However, these complaints are “unsupported”Executors often ask for contract amendments due to design’s errors. The company claims it occurs only due to bad faith of the contractorExecutors often ask for contract amendments due to design’s errors. The company claims it occurs only due to bad faith of the contractor
Are you familiar with the concepts of lean product development?Has never heard ofHas never heard of LPD, however, has heard about lean constructionHas never heard of LPD, however, has heard about lean construction
Are you familiar with the concepts of agile project management?Has never heard ofHas heard about it in lectures, however, the knowledge is reported as “shallow”Has heard about it in lectures, however, the knowledge is almost null
Are these methodologies applicable to your reality?Possibly, however, the implementation seems improbableImprobableVery applicable, however, difficulty in implementation would be significant
Which are the main challenges (or roadblocks) for the implementation of the methodologies, considering your companies context?Cultural. “The current way is working well”Cultural, functional organization structure, clients’ responsiveness, contractual structure (defined costs, deadlines and specifications)Cultural, contractual structure with the subcontracted designers and the impossibility of imposing methodologies in the suppliers