Table IV

Implementation of sustainable construction

IndicatorsMeanStandard deviationMean rank
(1) Implement environmental management system in construction work3.751.2312
(2) Implement occupational health and safety management system in construction work3.961.288
(3) Develop the concept of minimal construction waste produced during construction work3.541.2814
(4) Involve sub-contractors and suppliers who support sustainable principles3.931.169
(5) The construction work target is set under the capacity of the contractor4.440.991
(6) The construction work progress is in accordance with what is stated in the contract document3.991.315
(7) Check and test the required material and temporary work results to see if they comply with the specified technical specifications3.971.307
(8) Track project progress and always update it through a weekly checklist3.841.3411
(9) Review each construction work target to see if it meets the design document4.031.233
(10) Test all of the project results to see if they comply with the requirements contained in the contract document3.861.3110
(11) Testing of all project results is carried out by competent third parties together with the owners and users4.440.961
(12) Project owners and users maintain the construction work from the beginning3.861.2510
(13) Project owners and users acquire adequate training to utilize sustainable infrastructure before handover3.661.0713
(14) The contractor documents all the project processes that occur during the construction phase4.241.262
(15) The contractor prepares a final report on construction execution, including a manual for sustainable infrastructure utilization and maintenance4.021.354
(16) The contractor controls the construction execution through a checklist of integrated results between activities3.981.236

Note(s): Level of implementation 5 = often (mean = 4.51–5.00), 4 = sometimes (mean = 3.51–4.50), 3 = rarely (mean = 2.51–3.50), 2 = very rarely (mean = 1.51–2.50), 1 = never (mean = < 1.50)