Characteristics of the INNO case and sources of empirical data
| Case characteristics | ||
|---|---|---|
| Type of construction project | Appr 10,000 m2 office building within a Science Park on a university campus in Sweden | |
| No of collaborative innovation projects within the construction project | 11 innovation projects, e. g. Energy storage, Heat and cool systems, BIM in the facility management phase, and Wood construction frames | |
| No of strategic partners for the innovation projects | 7 | |
| No of innovation projects with external project leader / internal project leader | 5 / 6 | |
| Data collection | ||
| Time of data collection | 2017-2018 | |
| Interviews | 26 1,5 h Semi-structured interviews (14 in 2017, 12 in 2018) | |
| Reflective log-book | 8 project participants writing every 2nd week a short reflective log-book based on a digital platform | |
| Participatory observation | 35h of observations from meetings (15 h strategic meetings, 15h innovation project meetings, 5h construction project meetings) | |
| Documents | Project specific documents and corporate | |
| Case characteristics | ||
|---|---|---|