Sources of contractual disputes
| Sources of contractual disputes | Strongly disagree | Disagree | Neutral | Agree | Strongly agree | Mean score | Ranking |
|---|---|---|---|---|---|---|---|
| Ambiguous definition of the contract parties, the scope of their rights and obligations | 0 (0%) | 2 (3%) | 3 (5%) | 30 (52%) | 23 (40%) | 4.28 | 1 |
| Lack of precise arrangements regarding the calculation of contractual penalties for failure to meet the deadline | 0 (0%) | 0 (0%) | 4 (7%) | 36 (62%) | 18 (31%) | 4.24 | = 2 |
| Lack of detailed specification of the due date of works and specific milestones | 0 (0%) | 0 (0%) | 2 (3%) | 38 (66%) | 17 (29%) | 4.24 | = 2 |
| Lack of provisions regulating the introduction of changes to the project documentation during the construction stage | 0 (0%) | 0 (0%) | 5 (9%) | 35 (60%) | 18 (31%) | 4.22 | = 3 |
| Excessive amount of contractual penalties on contractor’s side | 0 (0%) | 0 (0%) | 4 (7%) | 37 (64%) | 17 (29%) | 4.22 | = 3 |
| Failure to specify the scope of the necessary documentation and the manner of informing the contractor about the activities | 0 (0%) | 0 (0%) | 5 (9%) | 37 (64%) | 16 (28%) | 4.19 | 4 |
| Lack of provisions regarding the rules of performing additional and replacement works and their settlement | 0 (0%) | 1 (2%) | 3 (5%) | 41 (71%) | 13 (22%) | 4.14 | 5 |
| Lack of detailed provisions regarding procedures to be followed for payment of remuneration and reporting defects | 0 (0%) | 1 (2%) | 4 (7%) | 40 (69%) | 13 (22%) | 4.12 | 6 |
| Inaccurate specification of the form of settlement | 0 (0%) | 1 (2%) | 2 (3%) | 45 (78%) | 10 (17%) | 4.10 | 7 |
| Lack of detailed regulations regarding the rights under the guarantee and warranty | 0 (0%) | 1 (2%) | 4 (7%) | 42 (72%) | 11 (19%) | 4.09 | 8 |
| Imprecise provisions regarding the contractual parties' security, e.g. the right to withdraw or terminate the contract | 0 (0%) | 1 (2%) | 4 (7%) | 43 (74%) | 10 (17%) | 4.07 | 9 |
| Inconsistency between the provisions of the contract | 0 (0%) | 1 (2%) | 6 (10%) | 43 (74%) | 8 (14%) | 4.00 | 10 |
| Sources of contractual disputes | Strongly disagree | Disagree | Neutral | Agree | Strongly agree | Mean score | Ranking |
|---|---|---|---|---|---|---|---|
| Ambiguous definition of the contract parties, the scope of their rights and obligations | 0 (0%) | 2 (3%) | 3 (5%) | 30 (52%) | 23 (40%) | 4.28 | 1 |
| Lack of precise arrangements regarding the calculation of contractual penalties for failure to meet the deadline | 0 (0%) | 0 (0%) | 4 (7%) | 36 (62%) | 18 (31%) | 4.24 | = 2 |
| Lack of detailed specification of the due date of works and specific milestones | 0 (0%) | 0 (0%) | 2 (3%) | 38 (66%) | 17 (29%) | 4.24 | = 2 |
| Lack of provisions regulating the introduction of changes to the project documentation during the construction stage | 0 (0%) | 0 (0%) | 5 (9%) | 35 (60%) | 18 (31%) | 4.22 | = 3 |
| Excessive amount of contractual penalties on contractor’s side | 0 (0%) | 0 (0%) | 4 (7%) | 37 (64%) | 17 (29%) | 4.22 | = 3 |
| Failure to specify the scope of the necessary documentation and the manner of informing the contractor about the activities | 0 (0%) | 0 (0%) | 5 (9%) | 37 (64%) | 16 (28%) | 4.19 | 4 |
| Lack of provisions regarding the rules of performing additional and replacement works and their settlement | 0 (0%) | 1 (2%) | 3 (5%) | 41 (71%) | 13 (22%) | 4.14 | 5 |
| Lack of detailed provisions regarding procedures to be followed for payment of remuneration and reporting defects | 0 (0%) | 1 (2%) | 4 (7%) | 40 (69%) | 13 (22%) | 4.12 | 6 |
| Inaccurate specification of the form of settlement | 0 (0%) | 1 (2%) | 2 (3%) | 45 (78%) | 10 (17%) | 4.10 | 7 |
| Lack of detailed regulations regarding the rights under the guarantee and warranty | 0 (0%) | 1 (2%) | 4 (7%) | 42 (72%) | 11 (19%) | 4.09 | 8 |
| Imprecise provisions regarding the contractual parties' security, e.g. the right to withdraw or terminate the contract | 0 (0%) | 1 (2%) | 4 (7%) | 43 (74%) | 10 (17%) | 4.07 | 9 |
| Inconsistency between the provisions of the contract | 0 (0%) | 1 (2%) | 6 (10%) | 43 (74%) | 8 (14%) | 4.00 | 10 |
As a benefit of your subscription, you can share temporary access to restricted articles.
Each link will stop working after 30 days or 10 uses. You may create up to 10 links in a 30 day period.
Please sign in to your personal account to gift article access.
As a benefit of your subscription, you can share temporary access to restricted articles.
Each link will stop working after 30 days or 10 uses. You may create up to 10 links in a 30 day period.
Gift articles remaining: --
Each link will stop working after 30 days or 10 uses. You may create up to 10 links in a 30 day period.
Gift articles remaining: --
As a benefit of your subscription, you can share temporary access to restricted articles.
Each link will stop working after 30 days or 10 uses.
You have reached the limit of 10 links within a 30 day period.
Sharing content requires targeting cookies to be enabled. Please update your cookie preferences to use this feature.