TableĀ 4

Contract Risk Management strategies

VariablesStrongly disagreeDisagreeNeutralAgreeStrongly agreeMean scoreRanking
Regular investigations at each phase of the project to reduce uncertainties0 (0%)0 (0%)3 (5%)25 (43%)30 (52%)4.471
Set up contingency plans0 (0%)0 (0%)3 (5%)28 (48%)27 (47%)4.412
Construction guarantee0 (0%)0 (0%)2 (3%)32 (55%)24 (41%)4.383
Extension of time claims0 (0%)1 (2%)2 (3%)30 (52%)25 (43%)4.364
Payment guarantee0 (0%)3 (5%)0 (0%)28 (48%)27 (47%)4.364
Retention0 (0%)2 (3%)2 (3%)28 (48%)26 (45%)4.345
Escalation clause0 (0%)2 (3%)2 (3%)31 (53%)23 (40%)4.296
Performance bond0 (0%)2 (3%)3 (5%)31 (53%)22 (38%)4.267
Professional indemnity0 (0%)1 (2%)6 (10%)34 (59%)17 (29%)4.168
Contract delay penalties0 (0%)3 (5%)5 (9%)32 (55%)18 (31%)4.129
Maintenance bond0 (0%)2 (3%)14 (24%)24 (41%)18 (31%)4.0010
Public liability insurance0 (0%)1 (2%)11 (19%)36 (62%)10 (17%)3.9511

or Create an Account

Close Modal
Close Modal

Gift article access

As a benefit of your subscription, you can share temporary access to restricted articles.

Each link will stop working after 30 days or 10 uses. You may create up to 10 links in a 30 day period.

Please sign in to your personal account to gift article access.

Register

Gift article access

As a benefit of your subscription, you can share temporary access to restricted articles.

Each link will stop working after 30 days or 10 uses. You may create up to 10 links in a 30 day period.

Gift articles remaining: --

Gift article access

Each link will stop working after 30 days or 10 uses. You may create up to 10 links in a 30 day period.

Gift articles remaining: --

Gift article access

As a benefit of your subscription, you can share temporary access to restricted articles.

Each link will stop working after 30 days or 10 uses.

You have reached the limit of 10 links within a 30 day period.