Background of participants for interview
| Portfolio | Code name | Organization | Hierarchy | Years of experience |
|---|---|---|---|---|
| Director (DT) | P1 | Public procurement authority | Senior | 33 |
| Deputy Director 1(DeT1) | P2 | Public procurement authority | Senior | 15 |
| Deputy Director 2(DeT2) | P3 | Public procurement authority | Senior | 20 |
| Senior officer (SF) | P4 | Public procurement authority | Middle | 18 |
| Junior officer (JF) | P5 | Public procurement authority | Junior | 13 |
| Municipal Works Engineer (EG. 8) | P6 | Municipal assembly | Senior | 25 |
| Procurement Officer (PO. 12) | P7 | District assembly | Middle | 10 |
| Quantity Surveyor (QS. 5) | P8 | Metropolitan assembly | Middle | 8 |
| Planning Officer (PF. 1) | P9 | Municipal assembly | Middle | 12 |
| District Works Engineer (EG. 6) | P10 | District assembly | Senior | 9 |
| Portfolio | Code name | Organization | Hierarchy | Years of experience |
|---|---|---|---|---|
| Director (DT) | P1 | Public procurement authority | Senior | 33 |
| Deputy Director 1(DeT1) | P2 | Public procurement authority | Senior | 15 |
| Deputy Director 2(DeT2) | P3 | Public procurement authority | Senior | 20 |
| Senior officer (SF) | P4 | Public procurement authority | Middle | 18 |
| Junior officer (JF) | P5 | Public procurement authority | Junior | 13 |
| Municipal Works Engineer (EG. 8) | P6 | Municipal assembly | Senior | 25 |
| Procurement Officer (PO. 12) | P7 | District assembly | Middle | 10 |
| Quantity Surveyor (QS. 5) | P8 | Metropolitan assembly | Middle | 8 |
| Planning Officer (PF. 1) | P9 | Municipal assembly | Middle | 12 |
| District Works Engineer (EG. 6) | P10 | District assembly | Senior | 9 |
Sharing content requires targeting cookies to be enabled. Please update your cookie preferences to use this feature.