Components of the cost model for the embankment preloading example
| Cost component | Description |
|---|---|
| Csur,i | Cost of adding a preloading surcharge of height ΔHi. Includes material costs, mobilisation costs, material availability at the time of the decision, and additional berms for slope stability |
| Cdelay | Cost penalty for project delay – that is, sufficient settlement (starget) has not been reached within a dedicated time period |
| COCR | Cost penalty for reduced serviceability of the superstructure, due to residual settlement caused by insufficient overconsolidation at time of unloading |
| Cost component | Description |
|---|---|
| Cost of adding a preloading surcharge of height Δ | |
| Cost penalty for project delay – that is, sufficient settlement ( | |
| Cost penalty for reduced serviceability of the superstructure, due to residual settlement caused by insufficient overconsolidation at time of unloading |