Table 1

Descriptive statistics (N = 35)

VariablesMeanMedianStd. Dev.MinMax
Inputs (collected)
Initial Performance measurement baseline (PMB) budget (in $M)473.4112.0976.93.13981.0
Final project cost (in $M)662.1150.01491.24.87500.0
Final cost performance index (unitless)0.940.980.120.601.1
Absolute value of change orders (in $M)37.511.061.60.0266.0
Initial baseline project/program duration (in months)50.348.020.78.096.0
Final project/program duration (in months)56.048.525.820.0132.0
Meeting business objectives (1–5 scale)4.14.01.11.05.0
Customer satisfaction (1–5 scale)4.14.01.11.05.0
EVMS helped proactively manage (1–5 scale)3.54.00.91.05.0
Outputs (calculated)
EVMS maturity score (out of 1,000)65770318278898
EVMS environment score (out of 1,000)657686158200897
Cost growth (in %)+56.1+13.0121.4−13.8+537.9
Cost growth, without change orders (in %)+9.9+0.036.7−51.6+147.1
Schedule growth (in %)+17.8+2.146.6−20.0+250.0
Change absolute value (in %)53.313.8122.20.0537.9

Source(s): Tables were created by the authors