Project performance metrics per EVMS maturity and environment heat map zone
| Performance metrics | Red | Orange | Yellow | Green | p-value |
|---|---|---|---|---|---|
| Cost growth (in %) | +92.3 | +48.1 | +13.7 | −0.3 | 0.007* |
| Cost growth, without change orders (in %) | +45.4 | +6.3 | +0.2 | −4.4 | 0.093 |
| Schedule growth (in %) | +24.3 | +26.9 | +3.7 | −5.9 | 0.102 |
| Change absolute value (in %) | 56.7 | 47.2 | 13.4 | 7.7 | 0.454 |
| Final cost performance index (unitless) | 0.85 | 0.95 | 0.95 | 1.03 | 0.091 |
| % of projects compliant with EIA-748-D | 20.0% | 71.5% | 100.0% | 100.0% | 0.007* |
| Meeting business objectives (1–5 scale) | 2.7 | 4.3 | 4.4 | 5.0 | 0.003* |
| Customer satisfaction (1–5 scale) | 2.7 | 4.3 | 4.4 | 5.0 | 0.007* |
| EVMS helped proactively manage (1–5 scale) | 2.7 | 3.5 | 3.9 | 4.0 | 0.105 |
| Performance metrics | Red | Orange | Yellow | Green | |
|---|---|---|---|---|---|
| Cost growth (in %) | +92.3 | +48.1 | +13.7 | −0.3 | 0.007* |
| Cost growth, without change orders (in %) | +45.4 | +6.3 | +0.2 | −4.4 | 0.093 |
| Schedule growth (in %) | +24.3 | +26.9 | +3.7 | −5.9 | 0.102 |
| Change absolute value (in %) | 56.7 | 47.2 | 13.4 | 7.7 | 0.454 |
| Final cost performance index (unitless) | 0.85 | 0.95 | 0.95 | 1.03 | 0.091 |
| % of projects compliant with EIA-748-D | 20.0% | 71.5% | 100.0% | 100.0% | 0.007* |
| Meeting business objectives (1–5 scale) | 2.7 | 4.3 | 4.4 | 5.0 | 0.003* |
| Customer satisfaction (1–5 scale) | 2.7 | 4.3 | 4.4 | 5.0 | 0.007* |
| EVMS helped proactively manage (1–5 scale) | 2.7 | 3.5 | 3.9 | 4.0 | 0.105 |
Note(s): *denotes p-values that are less than 0.05, meaning the observed differences between the heat map zones are statistically significant in this sample based on Kruskal–Wallis tests
Source(s): Tables were created by the authors